Where any building permit which has been issued by the Competent Authority before the commencement of this Code and where construction is in progress and has not been completed within the specified period from the date of such approval, the said permission shall be deemed to be sanctioned under this Code and shall only be eligible for revalidation thereunder. Accordingly, where the validity of sanction has expired and construction has not commenced, construction shall be governed by the provisions of this Building Code.
Annexure “B” – Standard Affidavit
I son/daughter/wife.., applied for building plan approval/ DPC Level/ occupation certificate vide application dated…… on Form BR………………….., and resident of …… …., hereby solemnly state & affirm as under:
That I shall not use basement as habitable space, as the same has not been included in the FAR and has not been shown as habitable space in the approved plans.
That I shall use the building only for the purpose for which approval and occupation certificate has been obtained.
That I shall comply with all the condition(s) implied by the competent authority at the time of approval of building Plan and Occupation certificate.
That …… ….(condition/ indemnity/ affirmity required by the Competent Authority)-I.
That … ….(condition/ indemnity/ affirmity required by the Competent Authority)-II.
That … …….(condition/ indemnity/ affirmity required by the Competent Authority)-III.
Place: Date:
DEPONENT
Verification
I son/daughter/wife of applied for building plan approval/ DPC Level/ occupation certificate vide application dated… on Form BR… and resident of …… …., hereby verify and affirm that the contents of this affidavit are true and correct to the best of my knowledge, belief and information in witness whereof I have signed hereunder on day of
Place: DEPONENT Date:
[112]
13.2Power of relaxation
The Government may relax any restrictions or conditions or norms stated in the Code or may issue direction to revise the Code, if the relaxation or revision is in public interest at large.
[108]
Appendix A
61 [Appendix A: Qualification and Competence of Architect/ Engineer/ Supervising Engineer/ Structural Engineer/ Proof Consultant/ Supervisor/ Geotechnical Engineer.
Sr.No.
Professional
Qualification
Competency/ Functions
1
Architect
Registered with valid membership of the Council of Architecture, India as prescribed under the Architect's Act 1972.
Prepare, sign all plans and submissions of building plans under Code 4 Further supervise construction of allbuildings and issue certificate of supervision and completion of all buildings pertaining to Architectural aspects, as stated in this code.
2
Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India) including Architectural Engineer as specified in clause A-2.2, Annex A of Part 2 Administration of National Building Code-2016.
Supervise all building construction including preparation of service plans, structural drawings, details and calculations of buildings upto 1000 square metres plot area and 15.0 metres height referred in Form BRV(A1).
3
Supervising Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India), with minimum three years of experience.
Supervise all building construction and issue certificate of supervision and completion of all buildings pertaining to structural aspects, as stated in this code.
4
Structural Engineer
Post-Graduate in Structural engineering from recognized Indian or Foreign University, having Associate membership of Institute of Engineer, India with
The Structural Engineer shall be competent to prepare the structural design, make calculations and design details for all
61Substituted vide memo no. Misc-2339-Loose-ULB-7/19/2023-2TCP dated 04.12.2023
[109]
minimum three years experience in structural engineering practice with designing and field work.
buildings referred in Form BR-V(A2).
5
Proof Consultant i i
i. Structural Engineer or a group/ firm of Structural Engineers having post-graduate qualification in structural engineering, having Associate membership of Institute of Engineer, India with ten years experience in structural design and evaluation thereof, for multi-storeyed and specialized structure, and/ or an institute of the following type: ii. Institute of Structural Engineers (India). ii. Central Building Research Institute, Roorkee. v. Various engineering institutes, like: a) Indian Institute of Technology; b) Punjab Engineering College, Chandigarh; c) National Institute of Technology; d) Any other institute of repute;
Evaluation/ checking of the structural design of the buildings referred in relevant Form BR-V(A2).
6
Supervisor
i. Two years diploma in Draftsman Civil with seven years experience under a qualified Architect/Civil Engineer for building design, construction and supervision; or ii. Three years diploma in Civil Engineering/Architectural Assistantship with five years experience under a
To prepare, sign and submit building plans and supervise construction of building upto 200 Sqm (8 marla) and 15 mtr. Height, under Code 4. The Supervisor shall get his/her empanelment renewed annually for the first 2 years and it shall be renewed for a period of 3 years thereafter.
[110]
qualified Architect/Civil Engineer for building design, construction and supervision; or iii) iii. B.Tech Civil, B.Tech (Building Engineering Management or equivalent);
7
Geotechnical Engineer
Post graduate in geotechnical engineering with minimum 10 year experience in geotechnical engineering practice in designing and field work. or Doctorate in civil engineering or geotechnical engineering with minimum 5 year experience in geotechnical engineering practice in designing and field work.
Evaluation/checking of the design of the buildings above 70 m height as mentioned in BR-V (A2)
“Note: Any post graduate qualification with at least 50% of the subjects relating to Structural Engineering (by credit), including research thesis, shall also be treated at par with Post Graduate in Structural Engineering.”]
[111]
Annexure “C” – Standard report format for Single Joint Inspection.
I. Inspection report Format for Pre-Construction Stage (to be conducted within 1-2 week of submission of building plan application/ self certification:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Geo-coordinates of site: Lat/ Long points: (as many required to survey the site)
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
HSIIDC
To be appointed by the Corporation.
Temporary Water Connection
Water Connection inspection
Town and Country Planning Dept.
District Town Planner
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
Forest Department
To be appointed by
Inspection for any acquisition or
As per Department requirement.
[113]
the Department.
grabbing of forest land or any cutting of marked trees.
II. Inspection report Format for During-Construction Stage (to be conducted within 1 week of submission of self certified DPC level certificate:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Labour Department
Joint Director/Deputy Director/Assistant Director
Cess Assessment inspection
As per Department requirement
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
Town and Country Planning Dept.
District Town Planner
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
HUDA
Junior Engineer
Inspection for temporary Water connection (only new construction) DPC level inspection (only new construction).