All building plan application submitted under Code 2.1 shall not be considered valid, unless made on the prescribed form and is accompanied with the requisite number of plans and documents, along with scrutiny fee and other charges (as prescribed by the Competent Authority). In case of non- compliance, the application together with plans and documents shall be returned to the applicant for resubmission in accordance with this Code.
4.3Validity of sanctioned plans
(1) Every sanction for the erection or re-erection of any building shall remain valid for two years in case of building height is less than 15 metres and for multi-storeyed buildings (fifteen metres or above in height) the sanction shall remain valid for five years from the date of sanction.
(2) If a building is not completed within two years (or five years, as the case may be) of the date of permission, the sanction will be deemed to have lapsed with respect to that portion of the building which has not been completed. In regard to the incomplete portion of a building, a fresh application shall be submitted in accordance with Code 2.1 and prescribed scrutiny fee.
(3) The temporary buildings, permitted by Competent Authority, shall not be allowed to stand three months beyond the validity of the sanctioned plans.
[29]
4.4 Re-validation of building plans
After sanction of building plan, in case the construction could not be started within two years (or five years, as the case may be) or has been started but could not be completed within the stipulated period, the owner/ applicant may apply for the revalidation of building plans before the sanction has lapsed simply by submitting re-validation fee @ Rs 10/- (rupees ten only) per square metre for the proposed covered area requested for re-validation. This revalidation of building plans be automatically considered from the date of submission of revalidation fee.
4.5 Deemed sanction
10[The Competent Authority shall pass an order within a period of twenty days of submission of building plans, accompanied by all necessary documents as mentioned in Code 2.1, either sanctioning or rejecting it. The building plan shall be deemed to be sanctioned, if it is in conformity with building Code and in accordance with the permitted land use of the area and all leviable fee/ charges have been deposited by the applicant but no orders have been passed by the Competent Authority within the specified time.
4.2Scrutinize and sanction of building plan
(1) The Competent Authority shall constitute such Committees for the purpose specified in Code 2.5, for scrutiny of applications received as specified under Code 2.1 and for submission of recommendations for sanction/ refusal of such applications.
(2) The Committee shall consist of officer/ official as decided by the Competent Authority and shall meet every week or as may be decided by the Competent Authority;
(3) The recommendations of the members of the committee shall be forwarded to the Competent Authority for consideration and approval, with or without change.
(4) The committee or any officer authorized shall pass on order and convey the decision of sanction or rejection in Form BR-III.
4.6Submission of revised building plans during the validity period of sanction
(1) If during the construction of a building, any deviation from the sanctioned plan is intended to be made, approval of the Competent Authority for the same may be obtained before the change is made. The revised plan showing the deviations shall be submitted and the procedure laid down for the sanction of building plan as stated in Code No. 2.1and2.2, shall be followed for all revised plans, along with the depositing balance scrutiny fee, if any.
(2) Any notice and building approval is not necessary for compoundable alterations/ violations, which do not otherwise violate any provisions regarding general building requirements, structural stability and fire safety requirements of this building Code.
10 Inserted/amended vide Misc-138A-Loose/7/5/2006-2TCP dated 22.12.2017
[30]
4.7 Revocation of sanction
The sanction granted under Code 4.2 can be revoked by the Competent Authority, if it is found that such sanction has been obtained by the owner by misrepresentation of material facts or fraudulent document submitted along with the building plan application or otherwise or the construction is not being done in accordance with the sanction granted.
4.8 Maintenance of E-Register for sanction/Registration of Building Plans
An online E-register shall be maintained for all building applications received, permissions given or deemed to have been given or refused or returned under this Code. The said register shall be available online to public for inspection on Departmental website.
4.9 Damp Proof Course certificate
11 [The owner (or the Architect, in case of self certification) shall submit a certification from an Architect (or by himself, in case of self certification) that the construction of building upto DPC level is as per sanctioned plan. The Competent Authority shall verify the certification and shall issue consent/ comments within seven days of receiving the certification. The DPC certificate shall deemed to be accepted, if it is in conformity with Code, but no consent/ comments have been passed by Competent Authority within specified time.
4.10Occupation Certificate
(1) Every person who intends to occupy such a building or part thereof shall apply for the occupation certificate in Form BR-IV(A) or BR-IV(B), which shall be accompanied by certificates in relevant Form BR-V(1) or BR-V(2) duly signed by the Architect and/ or the Engineer and along with following documents:
(i) Detail of sanctionable violations from the approved building plans, if any in the building, jointly signed by the owner, Architect and Engineer.
(ii) Complete Completion drawings or as-built drawings along with completion certificate from Architect as per Form BR-VI.
11 Inserted/amended vide Misc-138A-Loose/7/5/2006-2TCP dated 22.12.2017
[31]
(iii) Photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc/ DVD/ any other electronic media containing all photographs shall also be submitted.
(iv) Completion certificate from Bureau of Energy Efficiency (BEE) Certified Energy Auditor for installation of Rooftop Solar Photo Voltaic Power Plant in accordance to orders/ policies issued by the Renewable Energy Department from time to time.
(v) Completion Certificate from HAREDA or Bureau of Energy Efficiency (BEE) Certified Energy Auditor for constructing building in accordance to the provision of ECBC, wherever applicable.
(vi) No Objection Certificate (NOC) of fire safety of building from concerned Chief Fire Officer or an officer authorized for the purpose.
(2) No owner/ applicant shall occupy or allow any other person to occupy new building or part of a new building or any portion whatsoever, until such building or part thereof has been certified by the Competent Authority or by any officer authorized by him in this behalf as having been completed in accordance with the permission granted and an ‘Occupation Certificate’ has been issued in Form BR-VII. However, Competent Authority may also seek composition charges of compoundable violations which are compoundable before issuance of Form BR-VII. Further, the water, sewer and electricity connection be released only after issuance of said occupation certificate by the Competent Authority.
(3) The ‘Occupation Certificate’ shall be issued on the basis of parameters mentioned below:-
12(i)(a) For residential plots, minimum 25% of the total permissible ground coverage, shall be essential to be constructed to obtain occupation certificate, wherein one habitable room, a kitchen and a toilet forming part of submitted building plan is completed.
12Substituted vide Misc-2339 (ULB)-Vol-III/SD(DK)/2019/7/19/2019-2TCP dated 04.06.2019
[32]
(b)For Inland Container Depot (ICD) minimum area for considering approval of grant of occupation certificate shall be 2.5% of the permissible ground coverage.
(c)For other buildings, the minimum area norm for grant of occupation certificate shall be as under:-
Sr. No.
Area of site
Minimum area required for approval of building plan and grant of occupation certificate.
1
Upto 1 acre
25% of permitted coverage on all floors i.e. total permissible FAR.
2
Above 1 acre and upto 5 acres
20% of permitted coverage on all floors i.e. total permissible FAR.
3
Above 5 acres and upto 10 acres
15% of permitted coverage on all floors i.e. total permissible FAR.
4
Above 10 acres
10% of permitted coverage on all floors i.e. total permissible FAR.
Note: -The area to be constructed in all types of cases under category (i) (a), (b) and (c) above can be achieved either at ground floor or at subsequent floors.”
(ii) The debris and rubbish consequent upon the construction has been cleared from the site and its surroundings.
(4) 13[After receipt of application, the Competent Authority shall communicate in writing within eighteen days, his decision for grant/ refusal of such permission for occupation of the building in Form BR-VII. The E-register shall be maintained as specified in Code-4.8 for maintaining record in respect of Occupation Certificate.
(5) If no communication is received from the Competent Authority within 60 days of submitting the application for “Occupation Certificate”, the owner is permitted to occupy building, considering deemed issuance of “Occupation certificate” and the application Form BR-IV (A) or BR-IV(B) shall act as “Occupation Certificate”. However, the competent authority may check the violations made by the owner and take suitable action.
(6) If the owner or Architect or Engineer or Consultant as mentioned in Code 4.10(1)(i), (iv) and (v) as the case may be, submits a wrong report while making application under this Code or if any
13 Inserted/amended vide Misc-138A-Loose/7/5/2006-2TCP dated 22.12.2017
[33]
additional construction or violation is reported to exist at site or has concealed any fact or mis-represented regarding completion of construction of building along with its eligibility for seeking occupation certificate or before the completion of such report, he shall be jointly and severally held responsible for such omission and complaint against the Architect for suspension of his registration and the owner shall be liable to pay for the penalty as may be decided by the competent authority after giving an opportunity of hearing. Further, if it is emerged that the information is concealed by Engineer/ Consultant/ Owner, necessary penal proceedings will be initiated along with debarring Engineer/ Consultant/ Architect from practicing in the State of Haryana.
(7) 14The cases where building plans have been approved under Punjab Scheduled Roads & Controlled Areas Restriction of Unregulated Development Rules, 1965 i.e. prior to implementation of Building Code, and their applications for Occupation Certificates are being considered now as per Building Code, 2017, in such cases building plans should be considered as deemed approved as per the provisions of Haryana Building Code, 2017, subject to payment of composition charges