(1) The proportions of covered area of a building, including ancillary buildings, shall be in accordance with the plot categories given in following sub-Codes and the remaining portion shall be left open in the form of open space around the building.
(2) Core Areas
(i) 22[Residential
| Sr. no. | Plot area slabs | Maximum permissible Ground Coverage | Permissible basement | Maximum permissible Floor Area Ratio (FAR) | Maximum permissible Height (G+3 Floor) (including stilt (S+4 Floor)) (in metres) |
|---|---|---|---|---|---|
| 1 | Upto 60 square metres | 85% | Single level | 220 % | 16.5 |
21 Final amended substituted vide Misc-2339-(ULB)-VOL-II/7/5/2006-2TCP dated 06.11.2020.
22 Inserted/amended vide Misc-2339(ULB)-Vol-III/SD(DK)/2019/7/19/2019-2TCP dated 04.06.2019 and further amended on Misc-2339-VOL-III-ULB/7/5/2006-2TCP dated 20.10.2020.
[42]
| 2 | Above 60 to 150 square metres | 80% | Single level | 200 % | 16.5 |
|---|---|---|---|---|---|
| 3 | Above 150 to 225 square metres | 70% | Single level | 180% | 16.5 |
| 4 | Above 225 to 450 square metres | 60% | Single level | 160 % | 16.5 |
| 5 | Above 450 square metres | 50% | Single level | 140 % | 16.5] |
(ii) Commercial
| Sr. no. | Plot area slabs | Maximum permissible Ground Coverage | Permissible basement | Maximum permissible Floor Area Ratio (FAR) | Maximum permissible Height |
|---|---|---|---|---|---|
| 1 | upto 50 square metres | 100% | Single level | 200 % | Unrestricted |
| 2 | Above 50 to 150 square metres | 85% | Single level | 200 % | Unrestricted |
| 3 | Above 150 to 225 square metres | 75 % | Single level | 200 % | Unrestricted |
| 4 | Above 225 to 450 square metres | 60 % | Single level | 175 % | Unrestricted |
| 5 | Above 450 to 1000 square metres | 40% | Single level | 175 % | Unrestricted |
Note: Example for calculating FAR and ground coverage as per plot area slabs for 14 marla and 1 Kanal plot:
| Calculations for Ground Coverage | ||||
| Plot area slabs | Area in each slab (in square metres) | Maximum permissible Ground Coverage | 14 marla plot (354.1 square metres) | 1 Kanal plot (505.86 square metres) |
| Upto 75 | 75 | 66 | 49.5 | 49.5 |
| 76-100 | 24 | 66 | 15.84 | 15.84 |
| 101-150 | 49 | 60 | 29.4 | 29.4 |
| 151-250 | 99 | 60 | 59.4 | 59.4 |
| 251-350 | 99 | 50 | 49.5 | 49.5 |
| 351-500 | 149 | 50 | 4.05 | 74.5 |
| 501-1000 | 499 | 45 | 4.8861 | |
| 207.69 | 283.0261 | |||
| Actual permissible ground coverage | 58.6529229 | |||
[43]
| Calcul | ations for Floor Area R | atio (FAR) | ||
|---|---|---|---|---|
| Plot | Area in each | 1 | ||
| area | slab (in square | Maximum | Kanal(505. | |
| slabs | metres) | permissible Floor Area Ratio (FAR) | 14 marla(354.1 square metres) | 86 square metres) |
| Upto 75 | 75 | 165 | 123.75 | 123.75 |
| 76-100 | 24 | 165 | 39.6 | 39.6 |
| 101-150 | 49 | 145 | 71.05 | 71.05 |
| 151-250 | 99 | 145 | 143.55 | 143.55 |
| 251-350 | 99 | 125 | 123.75 | 123.75 |
| 351-500 | 149 | 120 | 9.72 | 178.8 |
| 501-1000 | 499 | 100Actual permissible FAR | 511.42144.4281276 | 10.858691.358136.6703699 |
(iii) Plot setbacks (core areas)
The buildings shall not project beyond the building lines as shown in the zoning plan of respective schemes. However, in case where zoning plans are not prepared, the minimum setbacks shall be provided as below:-
| Sr. No. | Area of plot (in square metres) | Minimum Front Setback (in metres) | Minimum Rear Setback (in metres) |
|---|---|---|---|
| 1. | Upto 60 square metres | 0.5 | 0.5 |
| 2. | Above 60 to 150 square metres | 1.5 | 1.0 |
| 3. | Above 150 to 225 square metres | 2.5 | 2.0 |
| 4. | Above 225 to 450 square metres | 3.0 | 3.0 |
| 5. | Above 450 square metres | 4.5 | 4.0 |
[44]
(a) The front setbacks can be adjusted to achieve permissible Ground Coverage subject to the condition that rear setbacks are fixed.
(b) In core areas single level basement may be allowedupto the maximum roof height of not more than 1.5 metres from the ground level for the area of maximum permissible coverage and after that till the zoned area, the roof of basement shall flush with the ground level.
(3)Areas other than core areas
(i) Residential
(a) 23[Plotted
| Sr. no. | Plot area slabs | Maximum permissible Ground Coverage | Permissible Basement | Maximum permissibl e Floor Area Ratio (FAR) | Maximum permissible Height (G+3 Floor) (including stilt (S+4 Floor)) (in metres) |
|---|---|---|---|---|---|
| 1 | Upto 100 square metres | 75% | Single level | 165 % | 16.5 |
| 2 | Above 100 to 250 square metres | 75% | Single level | 145 % | 16.5 |
| 3 | Above 250 to 350 square metres | 66% | Single level | 130 % | 16.5 |
| 4 | Above 350 to 500 square metres | 66 % | Single level | 120 % | 16.5 |
| 5 | Above 500 to 1000 square metres | 66 % | Single level | 100 % | 16.5] |
Note: -
I. The additional FAR is allowed on payment of charges as approved by Government from time to time.
II. Provided that the building shall conform to the restriction contained in the zoning plans or the architectural control sheets of respective area of sector.
III. Provided further that in case of sites measuring 100 square metres or less under any scheme relating to houses for economically weaker section framed by the Government, Housing Board, Improvement Trust or any other authority, the Competent Authority may relax the above condition.
IV. Provided further that the 25% of the built up area of the building or upto 50 square metres, whichever is less, can be used for non-nuisance professional consultancy services, after getting permission from Competent Authority in writing. The applicant
23Inserted/amended vide Misc-2339-ULB-Vol-II-A/7/5/2006-2TCP dated 25.04.2022. This amendment shall come into force from 25.04.2022.
[45]
shall apply for specific use of consultancy services as mentioned in Code 1.2(1)(lx) in Form N-I along with fee as mentioned inSchedule IV-A. The permission shall be granted in Form N-II”.
V. The stilts are permitted for parking purposes in residential and commercial plots of all sizes, subject to the condition that maximum permissible height of building shall not exceed 15 metres.
VI. 24[Any violation of the permissible ground coverage limits as indicated in the table above shall be non-compoundable.
VII. Plot setbacks (areas other than core areas)
| Sr. No | Area of Plot (in square metres) | Minium Front Setback (In meters) | Minimum Rear Setback (in meters) |
|---|---|---|---|
| 1. | Upto 75 square metres | 1.0 | 1.5 |
| 2. | Above 75upto 150 square metres | 1.5 | 2.0 |
| 3. | Above 150 upto 250 square metres | 2.0 | 2.0 |
| 4. | Above 250 square metres | 3.0 | 3.0 |
Note: No Balcony beyond the rear zoning shall be permitted]
(b) Group Housing
| Sr. No. | Maximum permissible ground coverage | Permissible Basement | Floor Area Ratio | Maximum Permissible height |
|---|---|---|---|---|
| 1. | 35% | Upto four levels | 175% | Unrestricted |
Note:
I. The height of mumty/ lift room/ water tank/Building MaintenanceUnit shall be exclusive of building height;
II. The parking requirement of group housing shall be governed by Code 7.1 or any other policy issued by the Government in this regard, from time to time.
III. 25[The siting and planning norms for Group Housing in Transit Oriented Development Zone (as defined in clause xciii-b of Code 1.2) shall be governed by clause 1 of Annexure D and policy notified on 09.02.2016, as amended from time to time.
IV. The siting and planning norms for Affordable Group Housing (as defined in clause ii-a of Code 1.2) shall be governed by clause 2 of Annexure D and policy notified on 19.08.2013, as amended from time to time.]
24Inserted/amended vide Misc-2339-ULB-Vol-II-A/7/5/2006-2TCP dated 25.04.2022. This amendment shall come into force from 25.04.2022.
25Inserted/amended vide Misc-2339-ULB-C/7/5/2006-2TCP dated 18.10.2022.
[46]
(ii) 26[Commercial
| Sr. no. | Type of building | Area norm | Maximum permissibl e Ground Coverage | Permissibl e Basement | Maximum permissibl e Floor Area Ratio (FAR) | Maximum permissible Height |
| 1 | Shop-cum-Flat (SCF) or Shop-cum-Office (SCO) or Shop-cum-Office-cum-Flat (SCOF) or Double Storey Shop (DSS) purposes or for shopping booths | Unrestricte d | As per the Architectural Control Sheets | |||
| 2 | Commercial colony: includes shopping mall, multiplex, Departmenta l store, Integrated commercial Complex, Service Apartment, starred Hotel/ Unstarred Hotel, offices. | Unrestricte d | 60 % | Unrestricte d | 175 % | Unrestricte d |
| 3 | Dhabas | 1000 square metres to 1 acres | 40 % | Unrestricte d | 40 %(maximum 50 sqm for kiosks like STD, Books, Cassettes, CDs etc.) | 5 metres |
| 4 | Banquet Hall | Minimum 2.5 acres | 50 % | Unrestricte d | 50%(10% FAR allowed for gift shop/STD | Unrestricte d |
26 Inserted/amended vide Misc-2339-ULB-Vol-II-A/7/5/2006-2TCP dated 25.04.2022. This amendment shall come into force from 25.04.2022.
[47]
| Booths, Toy Centre and flower shops etc.) | ||||||
| 5 | Starred Hotels, Restaurants | Unrestricte d | 40 % | Unrestricte d | 175 %(with permissible15%commercial component) | Unrestricte d |
| 6 | Restaurants | Minimum area 1000 square metres | 60% | Unrestricte d | 175 %(with permissible10%commercial component) | Unrestricte d |
| 7 | Amusement Park | Unrestricte d | 30 % | Unrestricte d | 50 %(with permissible15%commercial component) | Unrestricte d |
| 7 | Resort, Motel (with/ without banquet hall facilities) | Unrestricte d | 30% | Unrestricte d | 175 % | Unrestricte d |
| 8 | Big box retail stores | Unrestricte d | 60% | Unrestricte d | 175% | Unrestricte d |
| 9 | Petrol Stations | Unrestricte d | As per terms and conditions of Oil companies. | |||
27[Note:The siting and planning norms for Integrated Commercial Complex (as defined in the Act No. 8 of 1975) in Transit Oriented Development Zone (as defined in clause xciii-b of Code 1.2) shall be governed by clause 1 of Annexure D and policy notified on 09.02.2016, as amended from time to time.]
(iii) 28[Institutional and Educational
| Plot area slabs | Maximum permissible Ground Coverage | Permissible Basement | Maximum permissible Floor Area Ratio (FAR) | Maximum permissible Height |
|---|---|---|---|---|
| For all plot sizes | 35 % | Upto four levels | 150% | Unrestricted |
| Nurshing Home and Clinic Sites | 50% | Single level | 150 % | Unrestricted |
27 Inserted/amended vide Misc-2339-ULB-C/7/5/2006-2TCP dated 18.10.2022.
28 Inserted/amended vide Misc-2339-ULB-Vol-II-A/7/5/2006-2TCP dated 25.04.2022. This amendment shall come into force from 25.04.2022.
[48]
I. In case of educational institutes (College/ University/ Schools), the Hostel component is restricted to 20% of maximum permissible covered area, and
II. The residential component (i.e. residential facility for principal, teachers/ professors, staff, etc.) is restricted to 10% of maximum permissible covered area (separate from hostel component).
However, the Competent Authority after considering the requirement of the project can permit residential component above the stated percentage by recording the reasons, subject to maximum limit of 50% of FAR.
(iv) 29[Industrial and IT
| Sr. No. | Type of Industry | Maximum Ground Coverage | Permissible Basement | Maximum Permissible Floor Area Ratio | Maximum Permissible Height | Remar ks |
| 1. | General | 60% | Twin level | 150 % | 30 Metres | -- |
| 2. | Apparel and Footwear | 60% | Unrestricted | 250 % | Unrestricted | To be located on roads with a Right Of Way of 15 metres and above. |
| 3. | Biotechnolo gy other than Pharmaceuti cals | 40% | ||||
| 4. | Information Technology/Information Technology Enable Services | |||||
| 5. | Information Technology Park, Cyber Park, Cyber City, Technology Park | 40% | Unrestricted | 250 % | Unrestricted | Subject to conditi on that the plot must be located on roads with a Right Of Way of 30 metres and above. |
| 6. | Date Centre Industry | 60% | Unrestricted | 500% | Unrestricted There will be |
29 Substituted vide memo no. Misc-2339-Vol-III-ULB/7/5/2006-2TCP dated 25.04.2022.
[49]
| no restriction on floor to ceiling height subject to there being no mezzanine floor and compliance with structural and fire safety regulations.] |
|---|
Note for above Code 6.3(3)(ii), (iii) and (iv):
a. Unrestricted basement means as many numbers of basements subject to fulfilment of parking norms and/ or storage requirements and/ or use of maximum permissible FAR (in case of habitable use of basement) required in accordance to use of building.
b. Four levels basement shall be allowed only on-site having area more than 8000 square metres & in other cases as decided by Competent Authority.
c. The facility of enhanced FAR beyond the General level of 125%in industrial use shall be permissible on payment of proportionate charges/ infrastructure strengthening charges as prescribed by the Government/ Development Agency.
d. The facility of enhanced FAR of 25% beyond the General level of 150% in resorts, fivestar hotels, motels (with/without banquet hall facilities) shall be permissible on payment of proportionate charges/ infrastructure strengthening charges as prescribed by the Government/ Development Agency.
e. 30The facility of enhanced FAR of 50% beyond the general level of 100% in institutional and educational use shall be permissible subject to payment of proportionate increasing EDC & conversion charges at existing rates (in the form of augmentation charges) for the existing buildings i.e. Building Plans are approved before 30.06.2016. However, no such payment is required for such buildings whose building plans are approved by competent authority after 30.06.2016.
30Substituted vide Misc-2339-(ULB)-Vol-II /7/5/2006-2TCP dated 10.09.2019.
[50]
f. 31 [The following norms shall be applicable for Data Centres: -
(i) 32[For Data Centres, parking requirement of 1 ECS for 200 sqm of covered area will be provided in open area.]
(ii) Multi-level DG stacking upto G+4 structure shall be allowed subject to NOC from Fire Department and shall not be considered as part of FAR.
(iii)Chillers on the roof can be installed subject to structural safety and clearance from competent authorities/ Fire Department/ Airports Authority of India.
(iv)Boundary wall upto height 3.6m, with further 1m height for ‘Y’ fencing shall be permitted.
(v) Minimum number of windows subjects to compliance with building and fire safety regulations and having modern fire-fighting equipments installed within the premises.]
(v) Ware house/ Storage/ Godown
| Sr. no. | Type of building | Maximum permissible Ground coverage | Maximum permissible Floor Area Ratio (FAR) | Setbacks all around the plot (in metres) |
| 1 | Integrated Inland Container Depots/ Custom Bounded Areas | 60% | 75 % | 15 |
| 2 | Warehouse other than agricultural produces/ Grain Godowns/ Silos | 9 | ||
| 3 | Warehouse For Agricultural Produces/ Grain Godowns/ Silos | 6 | ||
| 4 | Gas Go-down | As per zoning plan |
Note:
If a warehouse contains storage of agro produce and also products other than agriculture produce, then the setbacks of 9 metres shall be followed.
31Inserted/amended vide Misc-2339-ULB-Vol-II-A/7/5/2006-2TCP dated 25.04.2022. This amendment shall come into force from 25.04.2022.
32Substituted vide Misc-720/2024/7/16/2024-TCP dated 25.07.2024
[51]
(vi) Recreational
| Sr. no. | Type of building | Area norms | Maximum permissible Ground coverage | Permissible basement | Maximum permissible Floor Area Ratio (FAR) | Maxmi mumpe rmissib le height |
|---|---|---|---|---|---|---|
| 1 | Recreational site in residential zone such as Club/ Community Centre including swimming pools, Badminton/ Tennis/ Squash Court, Indoor Games, Canteen/ Restaurant (not exceeding 200 square metres area) and related uses. Note: a. Not more than 10% of the permitted FAR to be allowed for rooms. b. Maximum 10% of the total FAR can be utilized for commercial use viz, Canteen/ Restaurants. | 0.5acre to2acres | 35 % | Single level | 100 % | Unrestri cted |
| 2 | Open Space Zone such as Mini Amusement Park, Outdoor games facility, Canteen (not exceeding 200 square metres area) and related infrastructure requiring minimal construction activity Note: The overall character of the site shall be maintained as open with minimum construction to be permitted at site. However, Joy rides/ water parks etc. Installed in such projects, which are open to sky shall not be considered to be part of covered area/ FAR. | 2acres to 5 acres | 10% | Single level | 10% | Unrestri cted |
[52]
(vii) Mixed land use
In case of mixed landuse site/ plot, the ground coverage, FAR, setback and other norms shall be in accordance with the zoning plan issued by Competent Authority.
33[Note: The siting and planning norms for Mixed land use in Transit Oriented Development Zone (as defined in clause xciii-b of Code 1.2) shall be governed by shall be governed by clause 1 of Annexure D and policy notified on 09.02.2016, as amended from time to time.]
(viii) General note: -
(a) The unrestricted height shall only be allowed subject to submission of No Objection Certificate from the appropriate authority (i.e. Defence Establishment, Air Force Establishment, Airport Authority of India, etc.), if any in the area.
Note: It is the responsibility of the competent authority to procure the zoning map/ instructions issued by the appropriate authority (i.e. Defence Establishment, Air Force Establishment, Airport Authority of India, etc.), if any present in its jurisdiction.
(b) The basement may be allowed to the maximum roof height of not more than 1.5 metres from the ground level for the foot print of the building and after that till the zoned area, the roof of basement shall be flush with the ground level.
(c) 34[The Additional FAR that can be availed by the applicant himself or by the purchaser of TDR Certificate (as defined in clause xciii-a of Code 1.2) shall be governed by clause 3 of Annexure D and policy notified on 16.11.2021, as amended from time to time.]
(d) 35[Electric Vehicle Charging Infrastructure shall be made free from FAR and minimum 2 Electric Vehicle charging points per 100 ECS (Equivalent Car Space) shall be made mandatory in Group Housing, Commercial and I.T. buildings.]