2.1 Planning Aspects
Construction planning aspects aim to identify and develop various stages of project execution on site which should be consistent with the management considerations. Planning aspects evolve out of the objectives of project and requirements of the final completed constructed facility. These objectives could relate to the final constraints, cost considerations, quality standards, safety standards, environmental considerations and health considerations. Construction practices would, then have to satisfy these objectives during construction phase of the project.
Having established objectives of the construction phase, planning determines processes, resources (including materials, equipments, human and environmental) and monitoring system to ensure that the practices are appropriately aligned. Adequate knowledge about pre-construction phase evolution of project, especially related to customer’s requirements, is an essential prerequisite for construction planning.
2.1.1 Preconstruction Phase
2.1.1.1 Besides the design aspects, preconstruction phase should also address all the issues related to the implementation of the design at the site through suitable construction strategy. During the design stage, the site conditions should be fully understood with anticipated difficulties and avoid the risk of subsequent delays and changes after the construction has started.
2.1.1.2 The selection of construction methods, building systems and materials, components, manpower and equipments and techniques are best done in the preconstruction phase. Such selection is influenced by the local conditions like terrain, climate, vulnerability for disasters, etc.
2.1.1.3 Construction in busy localities of cities needs
special considerations and meticulous planning due to restricted space, adjoining structures, underground utilities, traffic restrictions, noise and other environmental pollution and other specific site constraints.
2.1.1.4 The constructability aspects of the proposed construction methods needs to be carefully evaluated at the planning stage to ensure ease of construction besides optimizing the construction schedule and achieving quality, reliability and maintainability of the constructed facilities.
2.1.1.5 Constructional practices in hilly regions needs to take into considerations the problem of landslides, slope stability, drainage, etc, besides ensuring no adverse impact on the fragile environmental conditions.
2.1.1.6 Durability of constructions in corrosive atmospheric conditions like coastal regions and aggressive ground situations with high chlorides and sulphates should also be taken care of with appropriate constructional practices.
2.1.1.7 Constructional practices in disaster prone areas need specific planning. The type of construction, use of materials, construction techniques require special considerations in such areas.
2.1.1.8 Adverse weather conditions have strong bearing on construction phase. Situations wherein constructions are to be carried out in adverse weather conditions, such as heavy and continuous rain fall, extreme hot or cold weather, dust storms, etc, the practices have to address the relevant aspects. Accordingly, suitable design and field operations should be adapted or redefined in anticipation of these aspects. Some of these aspects are:
a) Site layout which enables accessibility in adverse weather.
b) Adequate protected storage for weather sensitive materials/equipments.
c) Protections to personnel from extreme hot/ control conditions.
d) Scheduling to allow maximization of outdoor activities during fair weather conditions.
e) Special design and construction provisions for activities in extreme temperature conditions like hot or cold weather concreting, staple of false work in extreme wind conditions (gusts).
f) Adequate lighting for shorter days in winter/ night work.
g) Design for early enclosure.
2.1.2 Resource Planning
Resource planning aims to identify requirement, availability and regulatory/control processes related to resources. Resource planning is a generic expression but the actual process of planning is specific to the resources considered.
In construction phases, the resources could be categorized as materials, manufactured products, equipments for construction, installation and fabrication, human resources as a part of overall organization, information resources, such as, reference standards and other practice documents, environmental conditions for work on site and infrastructure facilities. Therefore, the resource planning encompasses identification, estimation, scheduling and allocation of resources. Resource planning needs to establish a control system for controlling consumption monitoring, corrective action and resource reappropriation in the event of favourable deviation. Organizational capability, commitment to the project requirements and other constraints such as time and cost, need to be considered as inputs while planning resources. Techniques of management and planning, such as, Programme Evaluation and Review Technique (PERT) and Critical Path Method (CPM) (see Annex A) may be used.
Non-availability of basic building materials (brick, stone aggregate, etc) within reasonable lead would influence the constructional practice by alternative materials. The constructional practices also get decided by the local skills of the manpower for constructional activities. The equipment selection would also be governed by the site constraints. Therefore, as, the resource planning is critical to the project viability itself, the inputs to the resource planning need to be validated appropriately and established for such management. Resource planning should establish a proper system of data collection so as to facilitate effective resources control mechanism. Resource planning responsibility has to be specifically defined in the overall organizational setup.
2.1.3 Construction Phase
2.1.3.1 Organizational structure
The site management should be carried out through suitable site organization structure with roles and responsibilities assigned to the construction personnel for various construction related functions. Safety management is one of the important components of site management.
2.1.3.2 Site layout
The layout of the construction site should be carefully
planned keeping in view the various requirements to construction activities and the specific constraints in terms of its size, shape, topography, traffic and other restrictions, in public interest. A well planned site layout would enable safe smooth and efficient construction operations. The site layout should take into considerations the following factors:
a) Easy access and exit, with proper parking of vehicle and equipments during construction.
b) Properly located material stores for easy handling and storage.
c) Adequate stack areas for bulk construction materials.
d) Optimum location of plants and equipments (batching plants, etc).
e) Layout of temporary services (water, power, power suppression unit, hoists, cranes, elevators, etc).
f) Adequate yard lighting and lighting for night shifts.
g) Temporary buildings; site office and shelter for workforce with use of non-combustible materials as far as possible including emergency medical aids.
h) Roads for vehicular movement with effective drainage plan.
j) Construction safety with emergency access and evacuations and security measures.
k) Fabrication yards for reinforcement assembly, concrete precasting and shuttering materials.
m) Fencing, barricades and signages.
2.1.3.3 Access for fire fighting equipment vehicles
Access for fire fighting equipment shall be provided to the construction site at the start of construction and maintained until all construction work is completed.
2.1.3.3.1 Free access from the street to fire hydrants/ static water tanks, where available, shall be provided and maintained at all times.
2.1.3.3.2 No materials for construction shall be placed within 3 m of hydrants/static water tanks.
2.1.3.3.3 During building operations, free access to permanent, temporary or portable first-aid fire fighting equipment shall be maintained at all times.
2.1.3.4 Access to the upper floors during construction
In all buildings over two storeys high, at least one stairway shall be provided in usable condition at all times. This stairway shall be extended upward as each floor is completed. There shall be a handrail on the staircase.
2.1.3.5 Construction strategy and construction sequence
2.1.4 Scope Management
Construction management efforts should ensure that the project features and functions that characterise the project scope remain as established during the design finalization stage. Accordingly, construction phase practices need to be oriented to manage the project scope. As a part of overall project scope management functions, the processes of scope planning, scope definition and scope verification are associated with the preconstruction phase of the project. The scope monitoring and the change control are critical to the construction phase leading to serious implications on the time and cost aspects. In this respect, consolidated brief of the project established at the end of the design completion is an essential reference for scope baseline.