4.1 General:
The building envelope shall comply with the mandatory provisions of clause 4.2 and either the prescriptive criteria of clause 4.3 or the trade – off option of clause 4.4.
4.2 Mandatory Requirements:
4.2.1 Fenestration:
4.2.1.1 U- factors:
U-factors shall be determined for the overall fenestration product (including the sash and frame) in accordance with ISO- 15099, as specified in Appendix C, by an accredited independent laboratory, and labeled and certified by the manufacturer or other responsible party. U-factors for sloped glazing and skylights shall be determined at a slope of 20 degrees above the horizontal. For unrated products, use the default table in Appendix C. § 10
4.2.1.2 Solar Heat Gain Coefficient (SHGC):
SHGC shall be determined for the overall fenestration product (including the sash and frame) in accordance with ISO- 15099, as specified in Appendix C clause 11 by an accredited independent laboratory, and labeled and certified by the manufacturer or other responsible party:
Exceptions to clause 4.2.1.2:
(a) Shading Coefficient (SC) for the center glass alone multiplied by 0.86 is an acceptable alternate for compliance with the SHGC requirement for the overall fenestration area.
(b) Solar Heat Gain Coefficient (SHGC) for the glass alone is an acceptable alternate for compliance with the SHGC requirements for the overall fenestration product.
4.2.1.3 Air Leakage:
Air leakage for glazed swinging entrance doors and revolving doors shall not exceed 5 . 0 ~ I / s - m 2 . Air leakage for other fenestration and doors shall not exceed 2 . 0 s - m 2
4.2.2 Opaque Construction:
U-factors shall be determined from the default tables in Appendix C or determined from data or procedures contained in the ASHRAE fundamentals, 2005
4.2.3 Building Envelope Sealing:
The following areas of the enclosed building envelope shall be sealed, caulked, gasketed, or weather – stripped to minimize air leakage:
(a) Joints around fenestration and door frames;
(b) Openings between walls and foundations and between walls and roof and wall panels;
(c) Openings at penetrations of utility services through, roofs, walls, and floors;
(d) Site- built fenestration and doors;
(e) Building assemblies used as ducts or plenums; and
(f) All other openings in the building envelope.
4.3 Prescriptive Requirements:
4.3.1 Roofs:
Roofs shall comply with either the maximum assembly U- factor or the minimum insulation R- value in Table 4.1 R- value is for the insulation alone and does not include building materials or air films. The roof insulation shall not be located on a suspended ceiling with removable ceiling panels.
| Climate Zone | 24- Hour use buildings Hospitals, Hotels, Call Centers etc. | 24- Hour use buildings Hospitals, Hotels, Call Centers etc. | Daytime use buildings Other Buildings Types | Daytime use buildings Other Buildings Types |
| Climate Zone | Maximum U- factor of the overall assembly2 0(W/m - C) | Minimum R -value of insulation alone2 0(m - C / W) | Maximum U -factor of the overall assembly2 0(W/ m - C) | Minimum R-value of insulation alone2 0(m - C / W) |
| Composite | U-0.261 | R-3.5 | U-0.409 | R-2.1 |
| Hot and Dry | U-0.261 | R-3.5 | U-0.409 | R-2.1 |
| Warm and Humid | U-0.261 | R-3.5 | U-0.409 | R-2.1 |
| Moderate | U-0.409 | R-2.1 | U-0.409 | R-2.1 |
| Cold | U-0.261 | R-3.5 | U-0.409 | R-2.1 |
4.3.1.1 Cool Roofs:
Roofs with slopes less than 20 degrees shall have initial solar reflectance of not less than 0.70 and an initial emittance no less than 0.75. Solar reflectance shall be determined in accordance with ASTM E 903-96 and remittance shall be determined in accordance with ASTM E 408-71 ( RA 1996).
4.3.2 Opaque Walls:
Opaque walls shall comply with either the maximum assembly U-factor or the minimum insulation R-value in Table 4.2. R-value is for the insulation alone and does not include building materials or air films.
Table4-2: Opaque Wall Assembly U- factor and Insulation R-value Requirements
| Climate Zone | Hospitals, Hotels, Call Centers etc.(24- Hour) | Other Buildings Types (Daytime) | ||
| Maximum U-factor of the overall assembly (W/m2- 0C) | Minimum R -value of insulation alone (m2- 0C / W) | |||
4.4 Building Envelope Trade – Off Option:
The building envelope complies with the code if the building envelope performance factor (EPF) of the proposed design is less than the standard design, where the standard design exactly complies with the criteria in clause 4.3. The envelope trade – off equation is found in Appendix D.