(i) Width of Road or Means of access upto 18 meter Rupees 10/- per square meter of total covered area;
(ii) Width of Road or Means of access above 18 meter and Rupees 15/- per square upto 36 meter meter of total covered area;
(iii) Width of Road or Means of access above 36 meter Rupees 20/- per square meter of total Covered area;
(7) Fire Service Charge :
Building height
Fees
(i)
Upto 20 meters
Nil
(ii)
From 20 meters to 30 meters
2% of the building sanction fees
(iii)
Above 30 meters
5% of the building sanction fees
(8) All payments under these rules shall be made through account payee bank draft or account payee bankers cheque or account payee pay order drawn in favour of the New Town Kolkata Development Authority.
(9) Provided that re-sanction fees shall be restricted to 20% of the sanction fees calculated, subject to condition that, such re-sanction fees along with sanction fees paid earlier should not be less than plan sanction fees that would have been charged for fresh sanction. Scrutiny fee, increase of stacking fees and Fire Service charge if any shall be charged for each re-sanction of building plan.
Additional fee on building sanction fee:— Additional fee on building sanction fee will be levied if the application is submitted after the expiry of three years from the date of possession of the plot given by the Planning Authority Rate of such additional fee will be computed at rupees fifteen per square meter of the covered area per year counted from the date of expiry of three years from the date of taking over possession of the plot.
6A. As there is no provision of further re-validation of sanction after 10 years from the date of issuance of sanction even if no occupancy certificate / partial occupancy certificate issued earlier ; occupancy certificate / partial occupancy certificate shall be issued if the building is completed even after 10 years from the date of sanction, making additional payment of 15% of the original sanction fees.
Connection charges:— The Development Authority shall levy the following amenity charges:—
Table-I
Type
Size of Plot (in square meters)
Charges per connection ( in Rupees)
Charges per connection ( in Rupees)
Charges per connection ( in Rupees)
Type
Size of Plot (in square meters)
Residential use
Plot of other than residential use or educational use or institutional use
Plot of educational use or institutional use
Water Supply connection
Up to 500
Rs. 5000.00
Rs. 7500.00
Rs. 6000.00
Water Supply connection
Above 500 up to1500
Rs. 10000.00
Rs. 15000. 00
Rs. 12000.00
Water Supply connection
Above 1500 up to5000
Rs. 15000.00
Rs. 22500.00
Rs. 18000.00
Water Supply connection
Above 5000 up to10000
Rs. 20000. 00
Rs. 30000.00
Rs. 24000.00
Water Supply connection
Above 10000 up to 20000
Rs. 25000.00
Rs. 37500.00
Rs. 30000.00
Water Supply connection
Above 20000
Rs. 25000.00 plus Rs. 2500.00 per 10000 square meter or part thereof
Rs. 37500.00 plus Rs. 3750.00 per 10000 square meter or part thereof
Rs. 30000.00 plus Rs. 3000.00 per 10000 square meter or part thereof
Sewerage connection
Up to 500
Rs. 4000.00
Rs. 6000.00
Rs. 4800.00
Sewerage connection
Above 500 up to1500
Rs. 8000.00
Rs. 12000. 00
Rs. 9600.00
Type
Size of Plot (in square meters)
Charges per connection ( in Rupees)
Charges per connection ( in Rupees)
Charges per connection ( in Rupees)
Type
Size of Plot (in square meters)
Residential use
Plot of other than residential use or educational use institutional use
Plot of educational use or institutional use
Sewerage connection
Above 1500 up to5000
Rs. 12000.00
Rs. 18000.00
Rs. 14400.00
Sewerage connection
Above 5000 up to10000
Rs. 15000. 00
Rs. 22500.00
Rs. 18000.00
Sewerage connection
Above 10000 up to20000
Rs. 20000.00
Rs. 30000.00
Rs. 24000.00
Sewerage connection
Above 20000
Rs. 20000.00 plus Rs. 2000.00 per 10000 square meter or part thereof
Rs. 30000.00 plus Rs. 3000.00 per 10000 square meter or part thereof
Note : The above water supply connection charges are exclusive of ferrule and water meter charges.
Particulars of Drawings and Statements to be submitted :— (1) The hard copy drawings shall be ammonia prints and blue prints. One set out of total four sets of such drawings shall be blue printed. Prints of drawings shall be on only one side of the paper. One additional set of drawings and area statement shall be in the form of soft copy and to be submitted in Compact Disc duly signed by the Architect.
(2) The drawings shall be coloured as specified in Table below :—
Sl. No.
Item
Site Plan
Building Plan, Sections etc.
1.
Plot Lines
Thick Black
Thick Black
2.
Existing Road
Dark Green
-
3.
Future Road, if any
Green dotted
-
4.
Permissible building lines
Thick dotted Black
-
5.
Open spaces
-
-
6.
Existing work
Yellow
Yellow
7.
Work proposed to be demolished
Yellow Hatched
Yellow Hatched
8.
Proposed work
Red filled in
Red
9.
Drainage and Sewerage work
Red dotted
Red dotted
10.
Water supply work
Black dotted thin
Black dotted thin
11.
Greenery
Green wash
-
12.
Deviation
Red Hatch
Red Hatch
13.
Facilities
Violet
-
(3) An applicant intending to submit the proposal for sanction of building plan in the on-line system shall follow the colour code of drawings as per format uploaded in the website of the Development Authority.
Prohibition of sub-division and amalgamation of plots of land likely to affect the building operations:—
Amalgamation and sub-division of plots shall not be allowed.
Grant of sanction for erection of building:—Within a period of 60 (sixty) days from the date of receipt of the application under rule 4, completed in all respect, the Sanctioning Authority shall—
(a) accord sanction, for erection of building as specified in Schedule III ; or
(b) reject the application if it is not in accordance with the provisions of the Act and these rules:
Provided that rejection of an application to erect building shall not debar any applicant to make fresh application under rule 4.
Duration and expiry of a sanction:—(1) A sanction to erect building under these rules shall be valid for five years from the date on which it is sanctioned and may be renewed thereafter for a further period of five years on payment of fee at the rate of fifteen percent of the building sanction fee and on production of the previous sanction for erection of building.
(2) The sanction for erection of building may be revalidated further for a period of five years only, if the building operation has been partly completed and partial occupancy certificate has been issued, on production of the renewed previous sanction for building operation, the partial occupancy certificate and on receipt of 15% building sanction fees of the remaining portion.
Execution of erection of building:—(1) Not less than seven days before any person commences to erect building, the owner of the plot shall send to the Sanctioning Authority a written notice, in the form as specified in Schedule IV specifying the date on which he proposes to commence erection of building.
(2) From the date of commencement of erection of building till the date of issue of occupancy certificates, the applicant shall keep one set of the approved drawings at the work -site for checking by the Development Authority.
(3) An Officer of the Development Authority duly authorised shall inspect the work-site and issue necessary direction, if any, and also submit reports to the Development Authority for their information and further necessary action, if any.
(4) Within one month after the completion of erection of any building, the applicant shall inform the Sanctioning Authority of such completion of work by a Completion Notice in the form as specified in Schedule VII duly countersigned by the Architect, Civil Engineer or Structural Engineer, as the case may be. The notice shall be accompanied by four sets of hard copies and one soft copy of drawings with all the revisions and modifications duly signed by the applicant and Architect, Civil Engineer or Structural Engineer, as the case may be in the form of hard copy and marked as “Completion Plan”. A Structural Stability certificate shall accompany the notice and other certificates or documents as stated in the Schedules.
Chapter I
Short title, application and commencement :— (1) These rules may be called The New Town Kolkata (Building) Rules, 2009.
(2) They shall come into force on the date of their publication in the Official Gazette.
2 . Definitions :— (1) In these rules, unless the context otherwise requires,—
(a) "the Act" means the New Town Kolkata Development Authority Act, 2007 (West Ben. Act XXX of 2007);
(b) "apartment" means an independent dwelling unit with a kitchen or kitchenette or Pantry, sanitary toilet, ablution and washing spaces or part of a property having a direct exit to a street or a passage or to a common area leading to such street or passage which together with its undivided interest in the common areas and facilities forms an independent unit;
(c) "applicant" means Owner of the land and includes authorized representative of the owner or anybody having construction right in accordance with law and shall also include the transferee;
(d) "architect" means a person registered as such under the provisions of the Architects Act, 1972;
(e) "basement" means the lower storey of a building, partly or wholly below the ground level;
(f) "building" means a structure constructed for whatsoever purpose and of whatsoever materials, and includes the foundation, plinth, wall, floor, roof, chimney, fixed platform, veranda, balcony, chajja, cornice or projection or a part thereof or anything affixed thereto or any wall (other than boundary wall) enclosing or intended to enclose any land but does not include a tent, samiana or tarpaulin shelter erected for temporary use with the permission of the Development Authority;
(g) "Central business district and sub-central business districts" are the areas delineated by the planning authority as such;
(h) "chajja" or "cornice" or "weather shade" means a sloping or horizontal structural overhang usually provided over openings on external walls to provide protection from sun and rain or provided at any other level;
(i) "civil engineer" means a civil engineer having the qualifications and experience pre-scribed in sub-rule 2(ii) of rule 17;
(j) "clear height" shall be the vertical distance measured from the surface of the floor to the lowest point of the ceiling of the under side of any slab;
(k) "community parking" means the parking places for cars in residential areas for the use of the visitors, service peoples, doctors;
(ka) "construction and demolition waste" means the waste comprising of building materials, debris and rubble resulting from construction, re-modeling, repair and demolition of any civil structure.
(l) "covered area" means the horizontal area covered by a building at any floor subject to the exemption of the spaces as may be specified in these rules made under the Act;
(m) "courtyard" shall mean an area permanently open to sky enclosed partly or fully by one or more building and/or by walls;
(n) "cul-de-sac" means a public or private road closed at one end for vehicular traffic, with provision for turning;
(o) "Development Authority" means the New Town Kolkata Development Authority constituted under the Act;
(p) "dome" means a curve roof structure spanning an area; often spherical in shape and includes a square fabricated pan form; used in two ways joist concrete floor construction, a vault substantially hemispherical in shape, but sometime slightly pointed or bulbous; a ceiling of similar form;
(q) "electrical engineer" means an electrical engineer having qualifications and experience prescribed in rule 17;
(r) "electrical supervisor" means an electrical supervisor having qualifications and experience prescribed in rule 17;
(s) "floor area ratio" means the quotient obtained by dividing the total covered area on all floors, excluding areas stipulated in these rules, by the plot-area, viz.,
"Floor Area Ratio (F.A.R.)" = Total covered area on all floors Plot area
(t) "geo-technical engineer" means a geo-technical engineer having qualifications and experience as prescribed in rule 17;
(u) "ground coverage" means the quotient obtained by dividing the area of the plot covered by the building at the ground level by the total area of the plot, expressed as a percentage as follows :
"Ground coverage" = The area of the plot covered by building when vertically projected on the ground level × 100 Total area of the plot
(v) "ground level of a plot" shall be the average level of the center line of that portion of the means of access on which the plot abuts;
(w) "height of building" means the vertical distance measured from the average level of the center line of the means of access to which the plot abuts, to the highest point of the building whether with flat roof or sloped roof excluding appurtenant structures on the roof ;
(x) "inner courtyard" is a courtyard enclosed on all sides.
(y) "interpolation" means a method of calculating a new point between two or more existing data points;
(z) "IT/ITES business" that is to say, any plot containing building/s used principally for transaction of Information Technology/Information Technology Enabled System business;
(za) "kitchenette" means a cooking space or a cooking alcove;
(zb) "kiosk" means a small pavilion, usually open, built in gardens or parks. A similar structure, often enclosed, for the sale of merchandise such as newspaper or magazines;
(zc) "lift-well" means a vertical space for movement of lift-cage;
(zd) "means of access" means a road, giving access to the plot;
(ze) "minaret" means a tall tower in or contiguous to a mosque with stairs leading up to one or more balconies from which the faithful are called to prayer;
(zf) "online sanction" means communications that provide a real-time connection;
Explanation—For the purpose of this clause 'real-time' means the actual time during which something occurs relating to or denoting a system in which input data is available virtually immediately as feed back to the process for which it is coming.
(zg) "open space" means an area, forming an integral part of the plot at ground level and shall be open to the sky without any projection or overhang excepting cornices, chajjas or weather shades of not more than 0.075 mm width, which may be designated in different manner as follows :—
(i) "marginal open space of a building" means an open space at ground level forming an integral part of the plot between the extreme face of the building and the nearest boundary line of the plot. Marginal open space along the entire front face or rear face or the side faces of the building shall be designated as front open space, rear open space and side open spaces respectively. For this purpose, the front of the building shall be that face of the building which faces the means of access of the building and the rear of a building shall be deemed to be that face of the building, which is the farthest from the means of access;
(ii) "inter open space" means an open space in a plot measured between closest points of the two buildings when vertically projected on ground level;
(iii) "public open space" means any open space which is open to the use and enjoyment of the public, whether it is actually used or enjoyed by the public or not and whether the entry is regulated by charge or not;
(iv) "green open space" means an area open to sky and left uncovered so that greenery can grow as well as surface water can percolate underground;
(zh)"Outer courtyard" is a courtyard where one of the sides is not enclosed;
(zi) "parking" means an area provided to keep standing a vehicle. It may be covered, semi-covered or open. It may be private or public. It excludes parking space for repair generally called a garage;
(zj) "planning authority" means the planning authority declared under the West Bengal Town and Country (Planning and Development) Authority Act,1979;
(zk) "plumber" means a plumber having qualifications and experience prescribed in subrule 2(x) of rule 17;
(zl) "Public Health Engineer" means a Public Health Engineer having qualifications and experience prescribed in sub-rule 2(vi) of rule 17;
(zm) "rule" means a rule of these rules;
(zn) "Sanctioning Authority" for the purposes of the rules, means the Chairman of the Development Authority or such other officer of the Development Authority who may be empowered as such by Chairman of the Development Authority, by order;
(zo) "schedule" means a schedule appended to these rules;
(zp) "section" means section of the Act;
(zq) "stair-well" means a vertical space encircled by the flights of stair;
(zr) "Structural Engineer" means a structural engineer having qualifications and experience prescribed in rule 17;
(zs) "Town Planner" means a Town Planner having qualifications and experience prescribed in rule 17;
(zt) "toilet" means a room which is used both for bathing and water closet;
(zu) "Urban Designer" means an Urban Designer having qualifications and experience pre-scribed in rule 17;
(zv) "W.C." or "water closet" means a privy with arrangement for flushing the pan with water but does not include a bathroom;
(zw) "width of a road" means the whole width of space, including the service road (if any), footpath, open side drain and other features within the boundaries of the street, i.e., right of way.
(2) Words and expressions used and not defined in these rules, shall have the same meaning as respectively assigned to them in the Act.
Prohibition to erect building :— (1) No person shall erect any building until he takes over the possession of the land.
(2) The Development Authority shall give notice, in writing, if erection of any building is taken place in contravention of the provision of the Act and these rules and to stop such erection of building, and to remove unauthorized building or development :
Provided that the cost to be incurred on such removal shall be recovered in accordance with the provisions of the Bengal Public Demand Recovery Act, 1913 (Ben. Act III of 1913)
4 . Application for permission to erect building.— An application for permission to erect building shall consist of the following—
a) an applicant shall apply in the form specified in Schedule I, Schedule II, Schedule V and Schedule VI within three years from the date of possession of the land from the planning authority to the Sanctioning Authority to erect building, failing which additional fees for giving permission to erect building, may be levied;
b) forms and drawings as specified in Schedule I and Schedule II, shall be signed by the architect, civil engineer, structural engineer, town planner and urban designer as the case may be;
c) an applicant intending to avail himself of the on-line system may apply directly through website in the specified format uploaded thereof:
Provided that an applicant intending to avail himself of on-line system except uploading of drawings for building height below 15.1 metre and plot area upto 1500 square metre may apply directly through website in the specified format uploaded thereof. However, the applicant applied through website in the aforesaid partial on-line system will furnish the hard copies of the application mentioned in Schedules above.
Note : The Development Authority may, by order, specify the website for the purpose.
d) copies of other relevant documents, if any;
e) no objection certificate from the West Bengal Fire and Emergency Services, if applicable, along with original drawings containing the recommendation;
f) no objection certificate from the Airports Authority of India, wherever applicable;
g) Scrutiny fees as mentioned in sub-rule (5) of rule 5.
h) A certificate of the Architect to the effect that all the measures as prescribed in National Building Code (NBC)or as may be notified by the State Government or the Development Authority, from time to time regarding barrier free and accessibility features, incorporated in the building plan.
4A. Provision of Re-Sanctioning of existing building plan : (1) Notwithstanding anything contained in these rules —
(a) Where commencement of work has not been done on the basis of any building plan sanctioned under the rules in force before coming into force of these rules, no revalidation shall be allowed and the applicant may be asked to submit new proposal under these rules; and
(b) Where construction has been done partially and the previous sanctions has been obtained in conformity with these rules, re-sanction may be allowed on payment of requisite fees and charges.
(2) where construction has been commenced and the previous sanction of the building plan has been obtained in violation of the provisos of these rules, the re-sanction of the building plan shall be made under the provision of this rule on the request of the applicant:
Provided that if the building is already constructed, in part or in full, on the basis of such building plan which has been obtained in violation of the any provisions of these rules, shall be seized to exist unless the contradiction is removed and if the contradiction has not been removed, the re-sanction may be processed as per the provisions of respective rule under which the original plan has been sanctioned unless the applicant opts for sanction of building plan under these rules.
(3) The re-sanction of the existing building plan as mentioned in sub-rule (1) and (2), shall be valid only for 5 (five) years from the date of issuing re-sanction without provision of further revalidation.
Levy of fees for sanction of building plan :— (1) The Development Authority shall levy,—
(a) building sanction fees as specified in sub-rule (2).
(b) fees for occupancy certificate and partial occupancy certificate may be charged as specified in sub-rule (3) and sub-rule (4) respectively;
(c) stacking fees to be levied as specified in sub-rule (6);
(d) The Development Authority may allow the proposal for re-sanction of building plan, if it considers fit, on payment of such fees applicable under these rules, and plan sanction fee paid earlier shall be deducted subject to condition that there will be no refund of fee in any case;
Explanation.— Stacking fee for the purpose of this rule means a stacking fee payable in respect of stacking of building materials including building rubbish.
Note : Fifty percent of the building sanction fees shall have to be deposited for obtaining the sanction for the pile-work. if any.
(2) Building sanction fees payable for per square meter of covered area :—
(a) Residential use :
(i) Plots measuring up to 330 square meter;
(a) Rs. 75 per square meter if FAR is up to1.5;
(b) Rs.100 per square meter for FAR above 1.5 and upto allowable limit for the total FAR availed.
(ii) Plots measuring above 330 square
(a) Rs. 125 per square meter if FAR is upto
meter and up to 4000 square meter;
1.5;(b) Rs. 175 per square meter for FAR above1.5and upto allowable limit for the total FAR availed.
(iii) Plots measuring above 4000 square
(a) Rs. 200 per square meter if FAR is upto
meter;
1.5;(b) Rs. 300 per square meter for FAR above1.5and upto allowable limit for the total FAR availed.
(b) Educational use or Institutional use : Rs. 250 per square meter;
(c) Buildings other than Residential use, Educational use and Institutional use
(i) Rs. 400 per square meter if FAR is up to 1.5;
(ii) Rs. 600 per square meter for FAR above 1.5 and up to allowable limit for the total FAR availed.
(3) Fees for occupancy certificate :— The owner shall have to give notice of completion in the form specified in Schedule VII together with the fees prescribed below for obtaining occupancy certificate in the form specified in Schedule VIII by the Development Authority:-
(A) Buildings of residential use or educational use or institutional use :
(a) For floors below 15.1 meters in height :
(i) building in plot area upto 330 square meter Rs. 2000/- per building;
(ii) building in plot area above 330 square meter and upto Rs. 5000/- per building; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 7000/- per building; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 9000/- per building; upto 5650 square meter
(v) building in plot area above 5650 square meter Rs. 12000/- per building;
(b) For each additional floor of 15.1 meters and above in height or part thereof :
(i) building in plot area upto 330 square meter Rs. 300/- per floor;
(ii) building in plot area above 330 square meter and upto Rs. 500/- per floor; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 700/- per floor; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 900/- per floor; upto 5650 square meter
(v) building in plot area above 5650 square meter Rs. 1200/- per floor;
(B) Buildings other than residential use or educational use or institutional use :
(i) buildings in plot area upto 500 square meter Rs. 20000/- per building;
(ii) buildings in plot area above 500 square meter Rs. 22000/- per building;
(4) Fees for partial occupancy certificate :— The owner shall have to give notice of partial completion in the form specified in Schedule IX together with the fees prescribed below for obtaining partial occupancy certificate in the form specified in Schedule X by the Development Authority :—
A. Buildings of residential use, educational use or institutional use
(a) For floors below 15.1 meters in height
(i) building in plot area upto 330 square meter Rs. 1000/- per building;
(ii) building in plot area above 330 square meter and upto Rs. 2500/- per building; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 3500/- per building; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 4500/- per building; upto 5650 square meter
(v) Building in plot area above 5650 square meter Rs. 6000/- per building;
(b) For each additional floor of 15.1 meters and above in height or part thereof
(i) building in plot area upto 330 square meter Rs. 150/- per floor;
(ii) building in plot area above 330 square meter and upto Rs. 250/- per floor; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 350/- per floor; 1500 square meter
(iv) building in plot area above 1500 square meter and upto Rs. 450/- per floor; 5650 square meter
(v) building in plot area above 5650 square meter Rs. 600/- per floor;
B . Buildings other than residential use, educational use or institutional use:
(i) buildings in plot area upto 500 square meter Rs. 10000/- per building;
(ii) buildings in plot area above 500 square meter Rs. 11000/- per building;
(5) Scrutiny fee
(i) building in plot area upto 200 square meter Rs. 250/-;
(ii) building in plot area above 200 square meter and upto Rs. 350/-; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 1000/-; 5650 square meter
(iv) building in plot area above 5650 square meter Rs. 3000/-;
12A. Provision for construction material management & proper disposal of construction and demolition waste:
a) Storage of construction material: construction material should be stacked in an orderly manner as may be notified by the Development Authority from time to time.
b) Disposal of construction and demolition waste, slurries etc.
It shall be the responsibility of concerned owner, builder/ developer/ interested persons etc. that construction and demolition waste/ slurries are kept within the respective site till disposal. No construction & demolition wastes, slurries etc. shall be placed into the sewage, drainage and water supply pipelines. The construction & demolition waste, slurries shall not be stored or dumped in common public spaces (Viz, parks, play-grounds, footpath, service roads etc.) or in any vacant plot.
ii. The Development Authority may provide a paid service for disposal of construction and demolition waste subject to request in prescribed format by fixing a fee per ton payable by the owner, builder/ developer; interested person etc.
(b) The following shall be duties and responsibilities of the Civil Engineer:—
(i) supervision and execution of construction works as per drawings approved by the sanctioning authority and as per the submitted structural designs. He has also to submit declarations or undertakings as per the schedules and as required by Sanctioning Authority. He shall also have to certify the drawings as may be required by the Sanctioning Authority;
(ii) he shall prepare and submit structural details and design of buildings of height below 15.1 metres and must submit certificate of structural stability of such buildings as per subrule (b) or (c) of rule 4, as the case may be,
(iii) he shall prepare and submit plan and drawings for sanitary and plumbing arrangements for all buildings;
(iv) he shall be responsible for making adequate arrangements to ensure not only that the work is executed as per the approved plans but also is in conformity with the stipulations of the National Building Code and the BIS standards for safe and sound construction and non-hazardous functioning of the services incorporated in the building and for making adequate provisions for services and equipment for protection from fire hazards as per National Building Code and as per the recommendations of the West Bengal Fire and Emergency Services, if any. Civil Engineer shall also be responsible to ensure that the work is executed following the observations of the West Bengal Pollution Control Board and Civil Aviation Authority, as the case may be;
(v) he shall be responsible to ensure full quality control of all the works related to the construction, making suitable at-site test or laboratory tests of construction materials, concretes and maintain proper records of those;
(vi) he shall prepare the revised calculations and drawings in case of any revision with reference to the earlier submission of drawing and design as the case may be, if the same is warranted;
(vii) he shall be responsible for all the works executed by the contractors including legal matters relating to contracts or contractors along with the concerned Architect and other concerned professional(s) of the project.
c) Transportation of the construction material:
To prevent air pollution and for safety, construction material shall be transported in the manner as may be notified by the development authority by time to time.
d) If any person, the owner, builder/ developer/ interested person etc. violates the provision of rule 12A(a) & (b), a fine of Rs. 50,000 (rupees fifty thousand) only shall be levied and collected by the Development Authority in addition to the cost of proper disposal of the construction and demolition waste. In case of failure to pay the fine within the stipulated
time as may be notified by Development Authority, additional fine @ Rs. 10,000 (rupees ten thousand) only per day of delay shall be imposed.
e) If any person, the owner, builder/ developer/ interested person etc. violates the provision of rule 12A (c), a fine of Rs.5,000 (rupees five thousand) only shall be levied and collected by the Development Authority. In case of failure to pay the fine within the stipulated time as may be notified by Development Authority, additional fine @ Rs. 1,000 (rupees one thousand) only per day of delay shall be imposed.
Deviations during erection of building:—(1) No deviation from the sanction shall be made while erecting building.
(2) Notwithstanding anything contained in sub-rule (1),—
(a) if during execution of work with regard to erection of building, any internal alteration within the sanctioned covered space which does not violate the provisions of these rules made under the Act, is intended to be made, the applicant shall inform the Sanctioning Authority by notice in writing along with a certificate from the Architect and the Civil Engineer or Structural Engineer, together with drawings incorporating the deviations and structural drawings and calculations in case of structural deviations, stating the nature and purpose of such deviations at least fifteen days prior to carrying out such work, and may proceed with the execution of such work subject to the condition that such deviations shall be incorporated in the “Completion Plan” under sub-rule (4) of rule 12;
(b) if during execution of work with regard to erection of building any external deviation beyond the sanctioned covered space is intended to be made and which does not violate the provisions of these rules made under the Act, the applicant shall prior to carrying out such works, submit, in accordance with the provisions of these rules, a notice in writing along with a certificate from the Architect and the Civil Engineer or the Structural Engineer together with the drawings incorporating the deviations and structural drawings and calculations, and shall be accompanied with a fee not exceeding rupees five hundred per square meters of external deviation beyond the sanctioned covered space incorporating the deviations intended to be carried out, for necessary sanction thereof.
(3) If no notice is served under clause (a) of sub-rule (2) above, or execution of any work is undertaken without the sanction referred to in clause (b) of sub-rule (2) above, such execution of work shall be deemed to be in contravention to the provisions of the Act and these rules and shall be dealt with the provisions of the Act and the rules.
Occupancy certificate:—(1) Within fifteen days of the receipt of the completion notice, under sub-rule (4) of rule 12, the Sanctioning Authority after inspection will issue within one month of the said inspection, an Occupancy Certificate in the form as specified in Schedule VIII
(2) If the Occupancy Certificate under sub-rule (1) is refused, the Sanctioning Authority shall communicate in writing within one month, to the applicant stating therein the grounds of such refusal.
Partial Occupancy certificate:—(1) Whenever a request is made by the applicant to the Sanctioning Authority to occupy a part of a building or a building within a complex, which is under construction, Sanctioning Authority may allow partial occupancy and issue partial occupancy certificate as specified in Schedule X.
(2) A written request for the partial occupancy under these rules shall be accompanied by—
(a) a notice for partial completion in the form as specified in Schedule IX for the portion of the building or a building within a complex, which is proposed to be occupied;
(b) the structural stability certificate for the occupation of the portion of building or a building within a complex, which is proposed to be occupied.
(3) If the partial occupancy is refused under sub-rule (2), the Sanctioning Authority shall communicate the reasons thereof in writing to the applicant.
Validity of plan and notices:—Save as otherwise provided under these rules, no drawings submitted by an applicant shall be valid unless it is signed by the applicant and the concerned registered Architect and the Structural Engineer or Civil Engineer as specified in rule 17.
Engagement of technical persons for sanction of building plan and erection of building; and their qualifications, duties etc.:—(1) Every person who intends to undertake building operation shall have to engage technical persons as follows:—
2 hectares and / or buildings of height of 15.1 meters and above
(iii) Geo-technical Engineer (iv) Public Health Engineer or Environment Engineer (v) Electrical Engineer( only for buildings having height above 18 meters)
plot size above 2 hectares
(i) Architect (ii) Town Planner or Urban Designer (iii) Structural Engineer (iv) Geo-technical Engineer (v) Public Health Engineer to Environment Engineer (vi) Electrical Engineer
Note -Technical person engaged for a particular project may be changed by the owner with prior intimation to the Development Authority as well as the concerned Technical person.
(2) The qualification, experience, duties and responsibilities of Technical persons
(i) Architect
Rs. 24000.00 plus Rs. 2400.00 per 10000 square meter or part thereof
Drainage connection
Up to 500
Rs. 2000.00
Rs. 3000.00
Rs. 2400.00
Drainage connection
Above 500 up to1500
Rs. 4000.00
Rs. 6000. 00
Rs. 4800.00
Drainage connection
Above 1500 up to5000
Rs. 6000.00
Rs. 9000.00
Rs. 7200.00
Drainage connection
Above 5000 up to10000
Rs. 8000. 00
Rs. 12000.00
Rs. 9600.00
Drainage connection
Above 10000 up to 20000
Rs. 10000.00
Rs. 15000.00
Rs. 12000.00
Drainage connection
Above 20000
Rs. 10000.00 plus Rs. 1000.00 per 10000 square meter or part thereof
Rs. 15000.00 plus Rs. 1500.00 per 10000 square meter or part thereof
Rs. 12000.00 plus Rs. 1200.00 per 10000 square meter or part thereof
(iii) Structural Engineer
A Master's degree in Civil Engineering with specialization in Structural Engineering from a recognized University or Institute or its equivalent and at least two years experience in Structural design works. He must have proven track record for design of multi-storied buildings including design of deep foundations or basements;
A degree in Civil Engineering from any recognized University or Institute or its equivalent with at least seven years experience of structural design of buildings of height 15 metres above. He must have proven track record for design of multi-storied buildings including designs of deep foundations or basement.
(a) Minimum Qualification:—
A person must have registered under the provisions of the Architect's Act, 1972 (20 of 1972).
(b) The following shall be the duties and responsibilities of the Architect,—
(i) preparation and planning of all types of lay-outs and sub-mission of drawings and details including sub-mission of the proposal and notice of commencement and notice of completion and declaration as per the Schedules. He/She shall have to give undertakings as per the schedules and as required by the Sanctioning Authority. He/She shall also have to certify the drawings as may be required by the Sanctioning Authority.
(ii) he shall supervise the architectural design, execution and construction works as per specification and drawings approved by the Sanctioning Authority. He shall also be responsible to ensure that the work is executed and arrangements have been made as per the approved plans and also is in conformity with the stipulations of the National Building Code and the Bureau of Indian Standards for safe and sound construction and non-hazardous functioning of the services incorporated in the building and for making adequate provisions for services and equipment for protection from fire hazards as per the stipulations of the West Bengal Fire and Emergency Services, West Bengal Pollution Control Board and Civil Aviation Authority, as the case may be.
(iii) he shall be conversant with the provisions of the Act and rules made thereunder so that
all the submitted drawings, designs and lay-out etc. so prepared be in conformity with these rules.
(iv) he shall prepare the revised plan and drawings in case of any revision with reference to earlier submission of plan and drawings if the same is warranted. He shall submit partial completion and completion drawings.
(v) he shall be responsible for all the works executed by the contractors including legal matters relating to contractor along with the other professional(s) of the project;
(ii) Civil Engineer
A degree in Civil Engineering from any recognized University or Institute or any equivalent civil engineering qualification recognized by the Government and shall have at least two years experience in planning, design, and execution of building works including sanitary and plumbing works related to buildings;