- Short title, application and commencement :— (1) These rules may be called The New Town Kolkata (Building) Rules, 2009.
(2) They shall come into force on the date of their publication in the Official Gazette.
2 . Definitions :— (1) In these rules, unless the context otherwise requires,—
(a) "the Act" means the New Town Kolkata Development Authority Act, 2007 (West Ben. Act XXX of 2007);
(b) "apartment" means an independent dwelling unit with a kitchen or kitchenette or Pantry, sanitary toilet, ablution and washing spaces or part of a property having a direct exit to a street or a passage or to a common area leading to such street or passage which together with its undivided interest in the common areas and facilities forms an independent unit;
(c) "applicant" means Owner of the land and includes authorized representative of the owner or anybody having construction right in accordance with law and shall also include the transferee;
(d) "architect" means a person registered as such under the provisions of the Architects Act, 1972;
(e) "basement" means the lower storey of a building, partly or wholly below the ground level;
(f) "building" means a structure constructed for whatsoever purpose and of whatsoever materials, and includes the foundation, plinth, wall, floor, roof, chimney, fixed platform, veranda, balcony, chajja, cornice or projection or a part thereof or anything affixed thereto or any wall (other than boundary wall) enclosing or intended to enclose any land but does not include a tent, samiana or tarpaulin shelter erected for temporary use with the permission of the Development Authority;
(g) "Central business district and sub-central business districts" are the areas delineated by the planning authority as such;
(h) "chajja" or "cornice" or "weather shade" means a sloping or horizontal structural overhang usually provided over openings on external walls to provide protection from sun and rain or provided at any other level;
(i) "civil engineer" means a civil engineer having the qualifications and experience pre-scribed in sub-rule 2(ii) of rule 17;
(j) "clear height" shall be the vertical distance measured from the surface of the floor to the lowest point of the ceiling of the under side of any slab;
(k) "community parking" means the parking places for cars in residential areas for the use of the visitors, service peoples, doctors;
(ka) "construction and demolition waste" means the waste comprising of building materials, debris and rubble resulting from construction, re-modeling, repair and demolition of any civil structure.
(l) "covered area" means the horizontal area covered by a building at any floor subject to the exemption of the spaces as may be specified in these rules made under the Act;
(m) "courtyard" shall mean an area permanently open to sky enclosed partly or fully by one or more building and/or by walls;
(n) "cul-de-sac" means a public or private road closed at one end for vehicular traffic, with provision for turning;
(o) "Development Authority" means the New Town Kolkata Development Authority constituted under the Act;
(p) "dome" means a curve roof structure spanning an area; often spherical in shape and includes a square fabricated pan form; used in two ways joist concrete floor construction, a vault substantially hemispherical in shape, but sometime slightly pointed or bulbous; a ceiling of similar form;
(q) "electrical engineer" means an electrical engineer having qualifications and experience prescribed in rule 17;
(r) "electrical supervisor" means an electrical supervisor having qualifications and experience prescribed in rule 17;
(s) "floor area ratio" means the quotient obtained by dividing the total covered area on all floors, excluding areas stipulated in these rules, by the plot-area, viz.,
"Floor Area Ratio (F.A.R.)" = Total covered area on all floors Plot area
(t) "geo-technical engineer" means a geo-technical engineer having qualifications and experience as prescribed in rule 17;
(u) "ground coverage" means the quotient obtained by dividing the area of the plot covered by the building at the ground level by the total area of the plot, expressed as a percentage as follows :
"Ground coverage" = The area of the plot covered by building when vertically projected on the ground level × 100 Total area of the plot
(v) "ground level of a plot" shall be the average level of the center line of that portion of the means of access on which the plot abuts;
(w) "height of building" means the vertical distance measured from the average level of the center line of the means of access to which the plot abuts, to the highest point of the building whether with flat roof or sloped roof excluding appurtenant structures on the roof ;
(x) "inner courtyard" is a courtyard enclosed on all sides.
(y) "interpolation" means a method of calculating a new point between two or more existing data points;
(z) "IT/ITES business" that is to say, any plot containing building/s used principally for transaction of Information Technology/Information Technology Enabled System business;
(za) "kitchenette" means a cooking space or a cooking alcove;
(zb) "kiosk" means a small pavilion, usually open, built in gardens or parks. A similar structure, often enclosed, for the sale of merchandise such as newspaper or magazines;
(zc) "lift-well" means a vertical space for movement of lift-cage;
(zd) "means of access" means a road, giving access to the plot;
(ze) "minaret" means a tall tower in or contiguous to a mosque with stairs leading up to one or more balconies from which the faithful are called to prayer;
(zf) "online sanction" means communications that provide a real-time connection;
Explanation—For the purpose of this clause 'real-time' means the actual time during which something occurs relating to or denoting a system in which input data is available virtually immediately as feed back to the process for which it is coming.
(zg) "open space" means an area, forming an integral part of the plot at ground level and shall be open to the sky without any projection or overhang excepting cornices, chajjas or weather shades of not more than 0.075 mm width, which may be designated in different manner as follows :—
(i) "marginal open space of a building" means an open space at ground level forming an integral part of the plot between the extreme face of the building and the nearest boundary line of the plot. Marginal open space along the entire front face or rear face or the side faces of the building shall be designated as front open space, rear open space and side open spaces respectively. For this purpose, the front of the building shall be that face of the building which faces the means of access of the building and the rear of a building shall be deemed to be that face of the building, which is the farthest from the means of access;
(ii) "inter open space" means an open space in a plot measured between closest points of the two buildings when vertically projected on ground level;
(iii) "public open space" means any open space which is open to the use and enjoyment of the public, whether it is actually used or enjoyed by the public or not and whether the entry is regulated by charge or not;
(iv) "green open space" means an area open to sky and left uncovered so that greenery can grow as well as surface water can percolate underground;
(zh)"Outer courtyard" is a courtyard where one of the sides is not enclosed;
(zi) "parking" means an area provided to keep standing a vehicle. It may be covered, semi-covered or open. It may be private or public. It excludes parking space for repair generally called a garage;
(zj) "planning authority" means the planning authority declared under the West Bengal Town and Country (Planning and Development) Authority Act,1979;
(zk) "plumber" means a plumber having qualifications and experience prescribed in subrule 2(x) of rule 17;
(zl) "Public Health Engineer" means a Public Health Engineer having qualifications and experience prescribed in sub-rule 2(vi) of rule 17;
(zm) "rule" means a rule of these rules;
(zn) "Sanctioning Authority" for the purposes of the rules, means the Chairman of the Development Authority or such other officer of the Development Authority who may be empowered as such by Chairman of the Development Authority, by order;
(zo) "schedule" means a schedule appended to these rules;
(zp) "section" means section of the Act;
(zq) "stair-well" means a vertical space encircled by the flights of stair;
(zr) "Structural Engineer" means a structural engineer having qualifications and experience prescribed in rule 17;
(zs) "Town Planner" means a Town Planner having qualifications and experience prescribed in rule 17;
(zt) "toilet" means a room which is used both for bathing and water closet;
(zu) "Urban Designer" means an Urban Designer having qualifications and experience pre-scribed in rule 17;
(zv) "W.C." or "water closet" means a privy with arrangement for flushing the pan with water but does not include a bathroom;
(zw) "width of a road" means the whole width of space, including the service road (if any), footpath, open side drain and other features within the boundaries of the street, i.e., right of way.
(2) Words and expressions used and not defined in these rules, shall have the same meaning as respectively assigned to them in the Act.
- Prohibition to erect building :— (1) No person shall erect any building until he takes over the possession of the land.
(2) The Development Authority shall give notice, in writing, if erection of any building is taken place in contravention of the provision of the Act and these rules and to stop such erection of building, and to remove unauthorized building or development :
Provided that the cost to be incurred on such removal shall be recovered in accordance with the provisions of the Bengal Public Demand Recovery Act, 1913 (Ben. Act III of 1913)
4 . Application for permission to erect building.— An application for permission to erect building shall consist of the following—
a) an applicant shall apply in the form specified in Schedule I, Schedule II, Schedule V and Schedule VI within three years from the date of possession of the land from the planning authority to the Sanctioning Authority to erect building, failing which additional fees for giving permission to erect building, may be levied;
b) forms and drawings as specified in Schedule I and Schedule II, shall be signed by the architect, civil engineer, structural engineer, town planner and urban designer as the case may be;
c) an applicant intending to avail himself of the on-line system may apply directly through website in the specified format uploaded thereof:
Provided that an applicant intending to avail himself of on-line system except uploading of drawings for building height below 15.1 metre and plot area upto 1500 square metre may apply directly through website in the specified format uploaded thereof. However, the applicant applied through website in the aforesaid partial on-line system will furnish the hard copies of the application mentioned in Schedules above.
Note : The Development Authority may, by order, specify the website for the purpose.
d) copies of other relevant documents, if any;
e) no objection certificate from the West Bengal Fire and Emergency Services, if applicable, along with original drawings containing the recommendation;
f) no objection certificate from the Airports Authority of India, wherever applicable;
g) Scrutiny fees as mentioned in sub-rule (5) of rule 5.
h) A certificate of the Architect to the effect that all the measures as prescribed in National Building Code (NBC)or as may be notified by the State Government or the Development Authority, from time to time regarding barrier free and accessibility features, incorporated in the building plan.
4A. Provision of Re-Sanctioning of existing building plan : (1) Notwithstanding anything contained in these rules —
(a) Where commencement of work has not been done on the basis of any building plan sanctioned under the rules in force before coming into force of these rules, no revalidation shall be allowed and the applicant may be asked to submit new proposal under these rules; and
(b) Where construction has been done partially and the previous sanctions has been obtained in conformity with these rules, re-sanction may be allowed on payment of requisite fees and charges.
(2) where construction has been commenced and the previous sanction of the building plan has been obtained in violation of the provisos of these rules, the re-sanction of the building plan shall be made under the provision of this rule on the request of the applicant:
Provided that if the building is already constructed, in part or in full, on the basis of such building plan which has been obtained in violation of the any provisions of these rules, shall be seized to exist unless the contradiction is removed and if the contradiction has not been removed, the re-sanction may be processed as per the provisions of respective rule under which the original plan has been sanctioned unless the applicant opts for sanction of building plan under these rules.
(3) The re-sanction of the existing building plan as mentioned in sub-rule (1) and (2), shall be valid only for 5 (five) years from the date of issuing re-sanction without provision of further revalidation.
- Levy of fees for sanction of building plan :— (1) The Development Authority shall levy,—
(a) building sanction fees as specified in sub-rule (2).
(b) fees for occupancy certificate and partial occupancy certificate may be charged as specified in sub-rule (3) and sub-rule (4) respectively;
(c) stacking fees to be levied as specified in sub-rule (6);
(d) The Development Authority may allow the proposal for re-sanction of building plan, if it considers fit, on payment of such fees applicable under these rules, and plan sanction fee paid earlier shall be deducted subject to condition that there will be no refund of fee in any case;
Explanation.— Stacking fee for the purpose of this rule means a stacking fee payable in respect of stacking of building materials including building rubbish.
Note : Fifty percent of the building sanction fees shall have to be deposited for obtaining the sanction for the pile-work. if any.
(2) Building sanction fees payable for per square meter of covered area :—
(a) Residential use :
| (i) Plots measuring up to 330 square meter; | (a) Rs. 75 per square meter if FAR is up to1.5; |
| (b) Rs.100 per square meter for FAR above 1.5 and upto allowable limit for the total FAR availed. | |
| (ii) Plots measuring above 330 square | (a) Rs. 125 per square meter if FAR is upto |
| meter and up to 4000 square meter; | 1.5;(b) Rs. 175 per square meter for FAR above1.5and upto allowable limit for the total FAR availed. |
| (iii) Plots measuring above 4000 square | (a) Rs. 200 per square meter if FAR is upto |
| meter; | 1.5;(b) Rs. 300 per square meter for FAR above1.5and upto allowable limit for the total FAR availed. |
(b) Educational use or Institutional use : Rs. 250 per square meter;
(c) Buildings other than Residential use, Educational use and Institutional use
(i) Rs. 400 per square meter if FAR is up to 1.5;
(ii) Rs. 600 per square meter for FAR above 1.5 and up to allowable limit for the total FAR availed.
(3) Fees for occupancy certificate :— The owner shall have to give notice of completion in the form specified in Schedule VII together with the fees prescribed below for obtaining occupancy certificate in the form specified in Schedule VIII by the Development Authority:-
(A) Buildings of residential use or educational use or institutional use :
(a) For floors below 15.1 meters in height :
(i) building in plot area upto 330 square meter Rs. 2000/- per building;
(ii) building in plot area above 330 square meter and upto Rs. 5000/- per building; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 7000/- per building; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 9000/- per building; upto 5650 square meter
(v) building in plot area above 5650 square meter Rs. 12000/- per building;
(b) For each additional floor of 15.1 meters and above in height or part thereof :
(i) building in plot area upto 330 square meter Rs. 300/- per floor;
(ii) building in plot area above 330 square meter and upto Rs. 500/- per floor; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 700/- per floor; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 900/- per floor; upto 5650 square meter
(v) building in plot area above 5650 square meter Rs. 1200/- per floor;
(B) Buildings other than residential use or educational use or institutional use :
(i) buildings in plot area upto 500 square meter Rs. 20000/- per building;
(ii) buildings in plot area above 500 square meter Rs. 22000/- per building;
(4) Fees for partial occupancy certificate :— The owner shall have to give notice of partial completion in the form specified in Schedule IX together with the fees prescribed below for obtaining partial occupancy certificate in the form specified in Schedule X by the Development Authority :—
A. Buildings of residential use, educational use or institutional use
(a) For floors below 15.1 meters in height
(i) building in plot area upto 330 square meter Rs. 1000/- per building;
(ii) building in plot area above 330 square meter and upto Rs. 2500/- per building; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 3500/- per building; 1500 square meter
(iv) building in plot area above 1500 square meter and Rs. 4500/- per building; upto 5650 square meter
(v) Building in plot area above 5650 square meter Rs. 6000/- per building;
(b) For each additional floor of 15.1 meters and above in height or part thereof
(i) building in plot area upto 330 square meter Rs. 150/- per floor;
(ii) building in plot area above 330 square meter and upto Rs. 250/- per floor; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 350/- per floor; 1500 square meter
(iv) building in plot area above 1500 square meter and upto Rs. 450/- per floor; 5650 square meter
(v) building in plot area above 5650 square meter Rs. 600/- per floor;
B . Buildings other than residential use, educational use or institutional use:
(i) buildings in plot area upto 500 square meter Rs. 10000/- per building;
(ii) buildings in plot area above 500 square meter Rs. 11000/- per building;
(5) Scrutiny fee
(i) building in plot area upto 200 square meter Rs. 250/-;
(ii) building in plot area above 200 square meter and upto Rs. 350/-; 500 square meter
(iii) building in plot area above 500 square meter and upto Rs. 1000/-; 5650 square meter
(iv) building in plot area above 5650 square meter Rs. 3000/-;