Notice for Commencement of Construction
The Owner and the Architect on Record for the building shall notify the Competent Authority their intention to commence construction at least 7 working days prior to commencing construction by filing a Notice of Commencement of Construction, in the format prescribed in Form No. 10. Failure to notify the Competent Authority before commencing construction may result in lapse of the Development Permission.
A set of detailed working drawings including structural details based on approved building plans shall be submitted along with the Form. In the case of individual residential buildings up to G+2 on a plot not more than 500 sq.mt in size, the Competent Authority shall not enforce, on request of the owner/developer, to submit such details.
The Notice of Progress of Construction shall not be necessary in the following cases: i) Alteration in Building not involving the structural part of the building.
ii)Extension of existing residential building on the ground floor up to maximum area of 40 sq.mt.
On receipt of the Notice of Progress of Construction from the owner or developer, it shall be the duty of the Competent Authority, if found necessary, to check any deviation from the sanctioned plan and convey decision within 7 days to the owner or developer accordingly for compliance.
Development Permission may Lapse if Construction Not Commenced on Time
If the Competent Authority is not informed of commencement of work on a proposed building within twelve months of grant of Development Permission, the Development Permission shall lapse. Application for revalidation of Development Permission should be made within twelve months of grant of Development Permission. The extended period shall in no case exceed three years in the aggregate that is for a total period of four years. Procedure for obtaining a Revalidated Development Permission is specified in Regulation No.4.3.
Competent Authority to be Notified of Progress of Construction
The Owner or Developer and the Architect on Record or Engineer on Record shall be responsible for notifying the Competent Authority of progress of construction having been completed up to the stages stipulated in Schedule 13. Notice of Progress of Construction shall be made in the format prescribed in Form No. 11 and approved by the Persons on Record.
Risk Based Checks Inspections
The competent authority shall carryout the checking of the development permission application and the site inspection based on the consequence class specified.
Consequences Class.
Any development carried out by the owner or the developer attracts risk during the design and construction. Risk is defined, in the context of construction stages, as the likelihood of non-compliance with building regulations and the potential extent of harm to current and future users of building and the environment associated with non-compliance. The competent authority can, based on the extent carry out inspections based on the consequences class.
Principles of Risk Categorization
The different Consequences Classes is specified Table 5.5-1: Principles of Risk Categorization (Definition of Consequence Class) classification of the buildings & Control at the Design Stage (Design Supervision Levels, or DSL)
Based on the classification of the buildings specified in Table 5.5-2 the persons on record (POR) shall carryout the design supervision and the checks as specified in Table 5.5-2: Control at the Design Stage (Design Supervision Levels, or DSL)