- Restriction on construction of Multi-storied building.-(1) Construction of multi-storied building shall not be permitted villages/wards/municipalities/planning areas specified by the State Government. The Authority may include or exclude any other xareas for prohibition of multi storied building from time to time.
(2) The Authority may restrict construction of multistoried buildings in any other area on the basis of objective assessment of the available infrastructure and planning needs after obtaining due approval of the Government.
(3) Before commencement of these bye laws, where permission has been granted conditionally, such cases shall be dealt with under corresponding provisions of these Bye laws without any major change, or removal of construction, subject to the condition where violation of Heritage Zone conditions has occurred, this relaxation shall not apply.
(4) No Condonation in parking requirements, fire fighting provisions, health and structural safety requirements in case of development of Multi Storied buildings shall be allowed.
(5) In addition to the provisions of Part 4 Fire and Life Safety of National Building Code of India 2005 (Group 1), the Planning Authority may insist on suitable provisions in building from fire safety and fire fighting point of view depending on the occupancy and height of buildings in the case of Multi Storied building.
- Maintenance.-(1) In case of buildings with a height of 15.0 meters and above or ground coverage more than 500 sq m, the main entrance to the premises shall not be less than 5 (five) meters in width in order to allow easy access to fire engine. The gate, shall fold back against the compound wall of the premises, thus leaving the exterior access way, within the plot, free for the movement of fire service vehicles. If archway
Bihar Building Bye-Laws 40% Spin: 39% Lea 2/4/12/14 b h
-79-
is provided over the main entrances, the height of the archway shall not be less than 5 (five) meters.
(2) The space set apart for providing access within the premises shall, in no case, be included in the calculation of requirements pertaining to parking spaces and other amenities required to be provided for the building.
(3) Every access way shall be properly drained and lit to the satisfaction of the Authority. Manhole covers or any other fittings laid within the right of way of the access way shall be flushed with the finished surface level of it so as not to obstruct safe movement of men and vehicles.
(4) Reconstruction, addition or alteration to any multi-storied building shall not be taken in a manner, which shall reduce the width of the access way to a level below the minimum prescribed limit under these bye laws.
59. Structural Safety Design, Standards and other Services requirements.-(1) All buildings shall comply with the standards as mentioned below :
Structural Design: The structural design of foundation, elements of masonry, timber, plain concrete, reinforced concrete, pre-stressed concrete and structural steel shall be carried out in accordance with Part-6 of Group-2 structural design and related aspects, section-1 loads, forces and effects] section-2 soils and foundations, section-3 Timber and bamboo, 3A timber, 3B bamboo, section-4 masonry, section-5 concrete, 5A plain and reinforced concrete, 5B pre-stressed concrete and section-6 steel, section-7 prefabrication, systems building and mixed/composite construction, 7A prefabricated concrete, 7B systems building and mixed/composite construction of National Building Code of India, 2005 taking into consideration all relevant Indian Standards prescribed by Bureau of Indian Standards including the Indian Standard as given below for structural safety. In case of High Rise Buildings a Certificate of Under Taking for Hazard Safety Requirement shall be submitted in Form-XVI.
For General Structural Safety
-
IS: 456:2000 "Code of Practice for Plain and Reinforced Concrete
-
IS: 800-1984 "Code of Practice for General construction in Steel
-
IS: 801-1975 "Code of Practice for Use of Cold Formal Light Gauge Steel Structural Members in General Building Construction
-
IS 875 (Part 2): 1987 Design loads (other than earthquake) for buildings and structures Part 2 Imposed Loads
-
IS 875 (Part 3): 1987 Design loads (other than earthquake) for buildings and structures Part 3 Wind Loads
-
IS 875 (Part 4): 1987 Design loads (other than earthquake) for buildings and structures Part 4 Snow Loads
-
IS 875 (Part 5): 1987 Design loads (other than earthquake) for buildings and structures Part 5 special loads and load combination
-
IS: 883:1966 "Code of Practice for Design of Structural Timber in Building
-80-
-
IS: 1904:1987 "Code of Practice for Structural safety of Buildings: Foundation"
-
IS 1905:1987 "Code of Practice for Structural Safety of Buildings: Masonry Wall
-
IS 2911 (Part 1): Section 1: 1979 "Code of Practice for Design and Construction of Pile Foundation Section 1
For Earthquake Protection
-
IS: 1893-2002 "Criteria for Earthquake Resistant Design of Structures (Fifth Revision)"
-
Is: 13920-1993 “Ductile Detailing of Reinforced concrete Structures subjected to Seismic Forces – Code of Practice”
-
IS:4326-1993 "Earthquake Resistant Design and Construction of Buildings- Code of Practice (Second Revision)"
-
IS:13828-1993 "Improving Earthquake Resistance of Low Strength Masonry Buildings – Guidelines"
-
IS:13827-1993 "Improving Earthquake Resistance of Earthen Buildings – Guidelines",
-
IS:13935-1993 "Repair and Seismic Strengthening of Buildings - Guidelines"
(2) Quality of Materials and Workmanship: All material and workmanship shall be of good quality conforming generally to the accepted standards of Public Works Department and Indian standard specification and codes as included in Part-5 of Group-1 Building Materials and Part-7 of Group-3 Construction practices and safety of National Building Code of India.
(3) Alternative Materials, Methods of Design and Construction and Tests: The provisions of these bye laws are not intended to prevent the use of any material or method of design or construction not specifically prescribed by these bye laws provided any such alternative has been approved. The building materials approved by B.I.S. or any statutory body will form part of the approved building material and technology as part of the bye laws.
(4) Building Services
(A). The Planning design and installation of electrical installations, air conditioning installation of lifts and escalators can be carried out in accordance with Part-8 of Group-4 Building Services, section1-Lighting and Ventilation, section-2 Electrical and Allied Installations, section-3, Air conditioning and heating, section-4 acoustics, sound insulation and noise control, section-5 installation of lifts and escalators of National Building Code of India, 2005.
(B). The requirements of electric sub-station and the provision of electric sub-station shall also require approval from the concerned Authority.
(5) Plumbing Services

The planning, design, construction and installation of water supply, drainage and sanitation and gas supply system shall be in accordance with Part-9 of Group-5, Plumbing Services, section-1 water supply, drainage and sanitation (including solid waste management) section-2 gas supply of National Building Code of India 2005.