140 Repeal and Savings
(1) Subject to the provisions of sub-rule (2) with effect from the date of coming into the force of these rules, the rules as to the use of building sites and the execution of building work continuing to remain in force by virtue of the provisions of the clause (f) of sub section (2) of section 635 shall cease to continue to remain in force.
(2) Any application for sanction of any plan to erect a building submitted on or before the date on which the new rule would come into force in accordance with the provision of these rules and lying pending for sanction on that date shall not be rejected on the ground of the coming into force of these rules during the pendency of such application and every such application shall be considered in accordance with the provisions of the former rules.
(3) Notwithstanding such cesser, every building plan sanctioned under the former rules and remaining valid on the date immediately before the date of coming into force of these rules, shall continue to remain valid till the expiry of the period of validity thereof.
141 Removal of difficulties
If any difficulty or hardship arises in giving effect to any of the provisions of these rules, the Mayor-in-Council may, as occasion may require, by order, do or cause to be done anything or take such measure as may be necessary for removing the difficulty or hardship, on the basis of a set of guidelines to be framed hereafter by the Municipal Building Committee, as further recommended by the Corporation and approved by the State Government.
142 Old and insecure buildings
(1) The following relaxations of these rules will be available for construction of building in place and stead of existing buildings after demolition thereof :-
(a) FAR: Additional FAR to the tune of 50% 100% of the area presently occupied by the tenants(s) will be allowed over and above the FAR being presently utilized in the existing structure/Premies;
(b) Height: Normally the height of the re-erected building shall not be allowed to be more than 15.5 m unless the applicant is otherwise so entitled. However, this restriction on height may be relaxed as per the Act provided the proposal for re-erection complies with fire laws and provided further that additional car parking space as may be recommended by Municipal Building Committee is made available,
(c) Car Parking Space: At least 50% of the ground floor space of the re-erected building shall normally be earmarked for car parking space where construction of basement for car parking facilities is not feasible as per opinion of the Municipal Building Committee. However where construction of a basement is feasible as per opinion of the Municipal. Building Committee such basement may normally be earmarked for car parking space.
(2) The relaxations under sub-rule (1) above will be available only when the existing building which is to be demolished meets either of the following criteria:
(a) The building is more than 50 years and is partly or fully occupied by tenants, or
(b) The building is less than 50 years old but has rendered unfit for human habitation by natural forces, which building is also partly or fully occupied by tenants.
(b) the building which is upto 50 years old and declared unfit for human habitation by the appropriate authority, and when tenants demand, and are assured of equivalent amount of renewed space, post construction.
Explanation – for the purpose of this sub – clause, the appropriate authority shall be such as may be decided by the State Government.
(3) Every application for availing relaxation under sub-rule (1) has to be accompanied with documentary evidence of the tenants of the existing building signifying their consent to the demolition thereof:
(4) All applications for relaxation of Building Rules made under this rule have to be approved by the Municipal
67
Building Committee and its recommendations accepted by the Mayor-in-Council.
(5) The provisions of this rule will also apply to cases where more than one plot-owner applies after all such plots being amalgamated and mutated as per law.
(6) All other rules shall apply, mutatis mutandis.
143 Maintenance of Buildings
For all buildings older then 40 years, the owner of the building shall have to get the building inspected by a Structural Engineer within a year from the date of coming into force of these rules or within a year of the building becoming more than 40 years old if the building is not more than 40 years old at the time of commencement of these rules. The structural inspection report shall be furnished, by the owner to the Municipal Commissioner or to such officer and within such time as he may direct in this behalf, by public notice. Such report shall be valid for such period as may be fixed by the Municipal Commissioner and fresh report shall have to be obtained on its expiry. If any action for ensuring the structural safety and stability of the building is to be taken, as recommended by such Structural Engineer, the same shall be completed within such period as may be specified by him after giving notice to the Municipal Commissioner.
144 Rain Water Harvesting and Tree Cover
(1) Rain, Water Harvesting (RWH)
RWH system shall form a part of the building and shall have to be included in the plan, either for direct use of the rain water or for ground water recharging or both, in case of-
(i) new building or buildings or any housing complex as per Environmental Impact Assessment Guideline issued by the State Government/Government of India;
(ii) expansion of any existing building or buildings or housing complex, as per Environmental Impact Assessment Guidelines Issued by the State Government/Govt. of India.
This system shall comply with Central and State statutory requirements laid down in the relevant Acts and bye-Laws.
(2) Tree Cover
Provision for tree cover should be included in the plan for building sites -
(i) for any project covering a total floor area of 6000 sq. m or more, the applicant should arrange for raising and maintenance of tree cover at his own cost which should be at least 15% of the land area within the premises.
(ii) for any other project, having lesser total floor area, the tree cover should be reduced proportionately in the perspective of (i) above.
The applicant shall arrange to raise and maintain the plantation at his own cost and submit such programme to the Commissioner before the plan is approved.
145 Waste water recycling
Waste water recycling system shall be incorporated in all buildings including group housing as per Environmental Impact Assessment Guidelines Issued by the State Government/Govt. of India.
146 Provisions for physically handicapped or disabled persons
Notwithstanding anything contained elsewhere in these rules, there shall be provisions in all building plans of public utility buildings for disabled friendly devices like ramps with railing, toilet and drinking water facilities. Braille or auditory signals shall be provided in all lifts in accordance with the provisions of signage guideline laid down in National Building Code.
147 Provision for use of solar energy
Provision for use of solar energy in the form of solar heater and/or solar photo cells shall be included in building plans in case of any new building whose height is to exceed 15.5 m or expansion of any existing building if its height is to exceed 15.5 m.
Provided that use of solar water heater and solar power generation shall be mandatory as per government norms.
[PART I
Forms and Schedules the Kolkata Municipal Corporation for Buildings Schedule I [See Rule 4(2)]
Notice for erection / re-erection / addition to or alteration of a building
From (name and address of the applicant)
Name
Address
Phone No. Fax No. Email
Date:
To
Municipal Commissioner,
The Kolkata Municipal Corporation.
Subject: Notice for erection / re-erection / addition to or alteration Under section 393, 394 of Kolkata Municipal Corporation Act 1980 (strike out which is not applicable)
Sir,
I / We hereby give notice under the section specified above and intend to undertake the work as specified above under rule 4 of The Kolkata Municipal Corporation Building Rules, 2009. I/ We hereby request you to grant us necessary Building Permit under rule 15 of the Kolkata Municipal Corporation Building Rules, 2009.
In support of this notice, I / We wish to make the following statements: -
-
Assessee No.: ………………….. Borough No.: .……………… Ward No.: .…………
-
Premises No.: ……………
-
(i) Name of Owner(s): (a) Phone No.: (b) Address:
Phone No.: …………………….………………………………………………………………………………
(iii) Right in which Applicant in applying: Owner/ (any other right, please state and disclose proof)
-
Name of the Architect / L.B.S.: Class: .. No.: Phone No.: Fax: Email: Address :
-
(a) Name of Structural Engineer:
- Class: .... No.: .... Phone No.: .... Fax: .... Email: ....
- Address : ....
- (b) Name of Geo. Tech. Eng.: ....
- Class: .... No.: .... Address : ....
- Phone No.: .... Fax: .... Email: ....
-
- (1) (i) Area of land:
- (a) As per title document (m²) ....
- (b) As per physical measurement (m²) ....
- (iii) Boundaries of site on North ....
- South ....
- East ....
- West ....
-
- (2) Nature of land: Whether solid filled up tank or part tank? If tank specify the area, both solid/tank.
- .....