2.1 Development Permission Application
The Development Permission shall be for the compliance of GIFT Development Control Regulations regarding Planning Considerations, Urban Design Guidelines, Landscape Design Guidelines, Architectural Control, Services and Environmental, Health and Safety Guidelines.
A. Submissions:
Developer shall apply for the Development Permission as per the prescribed format and shall submit four set of hard copies along with soft copies prescribed as under:
32
i. Application for Development Permission (FORM: DP – A – 01) duly signed by the Developer
ii. True Attested copy of Letter of Allotment as issued by the GIFTCL
iii. True/Attested Copy of relevant documentation with GIFTCL establishing legal right to seek approval,
iv. UDAS as provided by the GIFTCL.
v. Drawings: Developer shall submit the soft-copies as well as four sets of hard-copies of Drawings as specified in Annexure-02 in the format as prescribed GIFTCL, signed by the Developer and the accredited professional, who shall indicate the name, address and the license number allotted by GIFTCL, with whom he is registered with.
vi. Area and Utility Statements: Area calculations, utilities statements, power requirements, DCS requirements and parking requirement for the building shall also be submitted in the prescribed format (FORM: DP – A – 02).
vii. Certificates of Accredited Professional as per FORM: DP – A – 03
viii. Reports stating provisions made in accordance with various guidelines provided by GIFTCL and these regulations :
Rainwater Harvesting
Fire Safety
Natural Light and Ventilation
• Operation and Maintenance
• IBMS
LEED compliance
Facilities for Physically Challenged
ix. Any other documents as specified by the GIFTCL in prescribed format
B. Grant or Rejection of Development Permission
33
If the Development Permission Application is not submitted in the prescribed format or is not accompanied with any of the above mentioned requisites, GIFTCL may not recommend the application to the Competent Authority.
On the recommendation of GIFTCL, the Competent Authority within a period of 90 calendar days may either grant or reject the Development Permission with the condition of submitting the detailed structural, MEP, Fire fighting, services, design and drawings and other reports as Competent Authority and/or GIFTCL may deem necessary.
C. Renewal of Development Permission
Development Permission granted under these Regulations shall be deemed to be lapsed, if such development work has not commenced on the site till the expiry of one year from the date of Development Permission. Provided that, the Competent Authority may on application along with NOC from GIFTCL, made to it before the expiry of above period (one year), extend such period by a further period of one year by charging Rs. 2.5 per sqm. of the Built-Up Area for the intended residential or institutional development or part thereof and at Rs. 5.00 per sqm of the Built-Up Area for the intended commercial development or part thereof, for renewal of Development Permission.
2.2 Commencement Certificate
The Commencement Certificate shall be sought only subsequent to the Development Permission. Developer shall submit the soft-copies and four sets of hard-copies of Detailed Drawings, Documents and statements regarding proposed development as specified in the Development Permission. All the Drawings, Statements, Specifications and Estimates shall be duly signed by the Developer, and the accredited professionals such as Architect, Structural Engineer, person retained for supervision etc. who shall write the name, address and license number allotted by the authority/agency, with whom the accredited professional is registered with.
A. Submissions:
Developer shall apply for the Commencement Certificate as per the prescribed format (FORM: CC – A – 01) as follows:
i. Development Permission
ii. Drawings as per Annexure- 03 in the format as prescribed by GIFTCL
iii. Certificates of Accredited Professional as per FORM: CC – A – 02 and FORM: CC – A – 03
iv. Report on EHS including Construction Manual, Construction Methodology and provisions during construction such as no nuisance, temporary structures, material stacking, movement, parking & installation of machinery, worker housing and safety in accordance with EHS Guidelines.
v. Insurance Policy: During construction, the developer by himself or through its contractor will take insurance coverage for the proposed building covering the construction period including third party liabilities. On the issue of Commencement Certificate, the Leaseholder will arrange to take insurance against fire/ natural disaster, including third
party liability and the same will be kept renewed from time to time to cover the entire lease period.
vi. Any other documents as specified by the Competent Authority and/or GIFTCL in the prescribed format
B. Issue of Commencement Certificate
Competent Authority on the recommendation of GIFTCL shall issue Commencement Certificate in the prescribed format with or without any conditions subject to satisfaction of the Competent Authority and/or GIFTCL with respect to compliance and submission made by Developer. The Commencement Certificate may be issued separately for Sub-Structure and Super-structure, if requested by the Developer subject to modification/changes in the works carried out by the Developer at his own cost.
i. Commencement Certificate for Sub-Structure: After third-party verification by empanelled consultant, Competent Authority on the recommendation of GIFTCL shall issue a commencement certificate for Sub Structure in prescribed format (FORM: CC – B – 01) within 90 calendar days of receipt of application for Commencement Certificate.
ii. Commencement Certificate for Super-Structure: On receipt of the Progress Certificate – Plinth Stage in prescribed format (FORM: PC – A – 01), GIFTCL will inspect the work and check any deviation from the approved plan and the details specified in these Regulations. GIFTCL after inspection will recommend the Competent Authority for issuance of commencement certificate for super structure with or without conditions within 15 days of receipt of Progress Certificate – Plinth Stage.
2.3 General Notation for Plan:
The notation generally used for plans shall be as per Annexure: 01.
2.4 Scrutiny Fee:
The Developer shall also have to pay scrutiny fees along with his application to GIFTCL at Rs. 5.00 per sqm. of the Built-Up Area for the intended Residential or Institutional development or part thereof and at Rs. 10.00 per sqm of the Built-Up Area for the intended Commercial development or part thereof. For Building Occupancy Certificate, the Developer shall have to pay scrutiny fees along with his application to GIFTCL at Rs. 5.00 per sqm of the Built-Up Area for the intended Residential or Institutional use or part thereof and at Rs. 10.00 per sqm of the Built-Up Area for the intended development or part thereof for Commercial use. The Developer shall have to bear the cost of the third party verification and shall have to pay an additional amount of 10% of the verification cost as supervision charges to GIFTCL for the same.
The scale of Scrutiny fees stated above is valid for a period of one year from the date of issue of notification approving the GDCR by the State Government. GIFTCL reserves rights to revise the above stated scrutiny fees from time to time as considered necessary.
2.5 Periodic Inspections during Construction
The Competent Authority and/or GIFTCL may at any time of erection of building or execution of any work or development, make an inspection thereof without giving previous notice of intention to do so.
Developer shall submit the progress certificate in the prescribed format (FORM: PC – A – 01, FORM: PC – A – 02, FORM: PC – A – 03 and FORM: PC – A – 04) through accredited professional. These shall be under taken as per guidelines and instructions issued by GIFTCL. Following shall be the recognized stages for Progress Certificates during construction:
i. Plinth
ii. First storey
iii. Middle storey in case of high-rise building
iv. Last storey
On receipt of the progress certificate from the accredited professional, GIFTCL may check any deviation from the approved plan which may require resubmission of amended plan for approval of the Competent Authority through GIFTCL and the details specified in these Regulations.
All the development work during construction shall be in accordance with the Environment, Health and Safety guidelines provided by GIFTCL.