Application for Revalidating a Development Permission shall be made by the Owner or Developer of the building, before the expiry of the Development Permission. The
revalidated period shall in no case exceed three years in the aggregate that is for a total period of four years.
Lapsed Development Permission may be revalidated after the expiry of the original Development
Permission, within a period of six months, with payment of penalty charges.
Revalidation of a Lapsed Development Permission after one and half year from the issue of the original Development Permission shall not be permitted. New application for Development Permission shall have to be made.
Fees
Development Permission Revalidation Fees for revalidating a Development Permission shall be determined by the Competent Authority and are listed in Schedule 9.
For revalidating a lapsed Development Permission, penalty charges shall be applicable and are listed in Schedule 9.
Documents
Documents to be submitted along with Application for Revalidating a Development Permission shall be determined by the Competent Authority and are listed in Schedule 10. The format for submission of documents is specified in Schedule 5.
The Competent Authority shall undertake scrutiny of the Application for Revalidating a Development Permission, in context of proposals of Development Plan of development authorities,as per development control regulation for D8 & D9 and communicate queries pertaining to the application.
Acceptance or rejection of responses to queries shall be communicated to the applicant.
Grant or Refusal of a Revalidated Development Permission
A Revalidated Development Permission in the format prescribed in Form No. 7 shall be issued to the applicant when the Competent Authority is satisfied that the design and specification of the proposed development comply with the Development Regulations. Reasons for grant or refusal of Revalidating a Development Permission shall be communicated to the applicant.
In case of any change to the Building‐unit which affects the approved layout or building blocks, Development Permission may not be revalidated. New application for Development Permission shall have to be made.
Penalties for not complying with Regulation No. 4.3 are stipulated in Schedule 6.