1. Short Title, Applicability & Commencement:
a) These Rules may be called Hyderabad Revised Building Rules, 2006
b) These rules shall be applicable to Municipal Corporation of Hyderabad area, rest of Hyderabad Urban Development Authority area, Hyderabad Airport Development Authority area, Cyberabad Development Authority area and Buddha Purnima Project Authority area and shall come into force from the date of publication of the Notification in the Andhra Pradesh Gazette.
c) These rules shall apply to all building activity. All existing rules, regulations, bylaws, orders that are in conflict or inconsistent with these Rules shall stand modified to the extent of the provisions of these rules.
2. Definitions:
(i) „Competent Authority‟ means:
(a) the Vice Chairman of the Hyderabad Urban Development Authority / Hyderabad Airport Development Authority / Cyberabad Development Authority/ Buddha Purnima Project Development Authority in the case of areas outside Municipal Corporation of Hyderabad area,
(b) the Commissioner, in the case of Municipal Corporation of Hyderabad area.
(ii) Enforcement Authority means the Commissioner of the Municipal Corporation of Hyderabad, the Commissioner of the Municipality or the Executive Authority of the Gram Panchayat in case of areas outside the municipal areas of the Development Authority or a Special Unit created for the purpose of sanctioning and monitoring building and development activity.
(iii) Parking Complex/Parking Lot means a premises either built or open which is utilized purely for parking of vehicles and where parking fees is collected by the owner and permitted in specific areas. The minimum site shall be 300 square meters.
(iv) Transferable Development Right (TDR) means an award specifying the built up area an owner of a site or plot can sell or dispose or utilize elsewhere, whose site or plot is required to be set apart or affected for a community amenity or development for public purpose in the Master Plan or in road widening or covered in recreational use zone, etc.. The award would be in the form of a TDR Certificate issued by the Competent Authority.
(v) High-Rise building means a building 18 meters or more in height. However, chimneys, cooling towers, boiler, rooms/ lift machine rooms, cold storage and other non-working areas in case of industrial buildings and water tanks, and architectural features in respect of other buildings may be permitted as a non-High Rise building. Buildings less than 18 m including stilt floor/parking floor stand excluded from the definition of high-rise buildings.
(vi) Height of building means height measured from the abutting road and in case of undulated terrain height can be considered as average of the corresponding ground level or formation level of proposed site.
(vii) ‘Sanctioning Authority‟ means the Commissioner of the Municipal Corporation of Hyderabad, the Commissioner of the Municipality or the Executive Authority of the Gram Panchayat in case of areas outside the municipal area of the Urban Development Authority or a Special Unit created for the purpose of sanctioning and monitoring building and development activity.
Terms and expressions which are not defined in these Rules shall have the same meaning as in the respective rules / regulations / by-laws of the respective local authorities and as defined in the National Building Code as the case may be, unless the context otherwise requires.
- Restriction on Minimum Building Plot Size along abutting roads in new developments and layouts:
There shall be restriction on the minimum building plot size along the abutting roads in all new developments areas and layouts.
TABLE I
| Abutting road | Minimum plot size | Max. Plot size |
|---|---|---|
| Right-of-way (in Mts.) | allowed (in sq. m) | allowed (in sq m) |
| 9 and below 12.2 | 100 | 2000 |
| 12.2 and below 18 | 200 | No Restriction |
| 18 and below 30 | 500 | No Restriction |
| 30 and above | 1000 | No Restriction |
Road Right-of-way means the total land width reserved for the road in the layout / Master Plan / Development Plan / Development Scheme whether the road is developed/formed or otherwise and includes the service road, if any, to be provided.
4.1 Minimum Approach road requirement for sites in new areas/layout areas:
No site or parcel of land shall be used for building activity unless it has a clear and established approach road of minimum 9 m Black topped Road is provided by the developer/builder/owner at his own cost or deposits the necessary cost for laying of the road by the sanctioning authority.