Provision of water supply for potable purposes as well as commercial and industrial uses, evacuation of used water and ensuring good sanitation are basic to economic development and safeguarding the health of the people of Chennai Metropolitan Area. This calls for integrated programmes and management efforts over the entire urban area covering the City, the Municipal Towns, the developing Urban Local Bodies and the new areas that will become urbanized.
B. Current Scenario
6.2 The present situation is that while the city corporation area is better served with water and sanitation infrastructure and facilities, the rest of the area suffers in comparison. The following table brings out the wide differences both in terms of public supply of drinking water to resident population and sewerage and sanitation systems.
Table No. 6.1 Water Supply and Sewer Current Scenario in Selected Municipalities in CMA
Area
Max. Water Availability million litres per day 2007
Per capita Supply Best of Times (lpcd)
Extent of Sewered Area %
Effluent Treated million litres per day 2007
Chennai City
645
107
99
486
Selected Municipal Towns
Thiruvottiyur
30
11
No UGD (for a part)
No Treatment plant
Madhavaram
5
54
No UGD
No Treatment plant
Pallavaram
5
46
No UGD
No Treatment plant
Ambattur
4
27
No UGD
No Treatment plant
Source: Commissioner of Municipal Administration
6.3 While the supply side situation overall is as above the availability of services for the poorer sections is minimal. Even in the better-serviced City area most of the slum settlements – more than 90% of slum households – receive water from metro tankers (according to a recent study). In spite of near 100% underground sewerage available in the City, the toilets (including community/public latrines) connected to the sewer system cover only 77.5% of slum households. According to a recent survey, less then 30% of slum households have individual latrine facilities.
Quality of Water
6.4 The following Table shows the quality of water supplied by Metro water to the City.
Table No. 6.2 Quality of Water Supplied by CMWSSB in Chennai city
Principal Parameters of Quality
WHO Standard
Quality As Realised at Consumer End
1. Turbidity (NTU)
10 Max
5
2. Colour (unit on platinum cobalt scale)
25 Max
Colourless
3. Total Dissolved Solids (mg per litre maximum)
2000 Max
370
Source: CMWSSB
6.5 The Metro water gets the water supply from a diverse number of sources from lakes and tanks fed by monsoon, underground aquifers as well as distant sources such as from Krishna River and Veeranam Lake. In addition water is sourced from open and shallow wells, bore-wells not only from the CMA but also from places outside by individuals, institutions and water tanker operators. The following Table shows these different Metro water sources.
Table No. 6.3 Sources and Availability of water
Source
Quantity in Mld
Public
200
Poondi, Sholavaram, Red Hills Lake System (including
diversion of flood flow from Araniyar to Korataliyar
Ground Water from Northern Well Fields
100
Southern Coastal Aquifer
5
Sub Total (A)
305
Krishna Water I Stage
400
Krishna Water II Stage
530
New Veeranam (CWSAP-I)
180
CWSAP-II (Proposed)
20
Sea Water Desalination (Proposed)
200
Sub Total (B)
1330
Grand Total (A) + (B)
1635
Mark II hand pumps (public)
6970 Nos.
Source:CMWSSB
6.6 The salient features of the Sewerage Macro System Units are given below: All the locations except Nesapakkam are at the edge of the City. The total treatment capacity is 481 MLD per day as against an estimated sewage generation of at least 700 MLD.
Table No. 6.4 Salient Features of the Sewerage Macro Systems Treatment Units
Zone
Location
Type
Capacity (mld)
I
Kodungaiyur
Activated Sludge Plant
270
II
Kodungaiyur
Activated Sludge Plant
III
Koyambedu
Activated Sludge Plant
94
IV
Nesapakkam
Activated Sludge Plant
63
V
Perungudi
Activated Sludge Plant
54
Total
481
Source: CMWSSB
6.7 Localised sewerage systems are in existence in Alandur, Valasaravakkam, and Ambattur. Several of them are partial and a few of them have just been completed. In respect of the local bodies of Pallavaram, Tambaram, Madhavaram, Kathivakkam, Porur,
Ullagaram, Puzhithivakkam, Avadi, Maduravoyal and Thiruvottiyur proposals have been formulated for instituting underground sewerage systems.
6.8 Metro water has taken up the development of water supply and sewerage system along the IT Corridor being established south of Chennai for a projected future demand of 50 MLD. Concurrently an underground sewerage system is also proposed. This corridor will include a number of Town and Village Panchayats on both sides of the Rajiv Gandhi Salai (OMR).
Equity Considerations
6.9 In the present system there is a wide disparity in the quantity, quality and timing and methods of water supply as between the general category of consumers and consumers with low affordability. It should be the effort to design a system based on use for drinking purposes and personal hygiene as common to all groups and requirements for sanitation depending upon the quantities for toilet flushing. Even in the European context many of the cities are proposing a supply of between 100 and120 lpcd for residential supply with nearly 50% sourced from recycled water for toilet flushing.
6.10 According to the Chennai Metropolitan Water Supply and Sewerage Act Metro water is responsible for supply of protected water and provision of sewerage facilities over the whole of CMA extending to 1189 sq.km. However presently its activities are confined to the City Corporation limits within 176 sq.km. and a further 8 sq.km. in the immediate environment of the City. Metrowater should strive to extend its operations gradually to cover the entire CMA. The principal stakeholders in the public sector in the rest of the CMA are the local bodies, municipalities and town and village Panchayats. These local bodies are mainly responsible only for maintenance of the system and distribution installed by Tamil Nadu Water Supply and Drainage Board (TWAD) a parastatal organization. Recently however Government has directed the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) to be the nodal agency for execution and maintenance of underground sewerage schemes in the adjacent and distant urban areas within the CMA. Under this directive CMWSSB is required to develop proposals for execution of a comprehensive sewerage system for the entire metropolitan area in addition to existing sewerage system in Chennai.
6.11 In the private sector apart from individuals and institutions tanker contractors and bottled water suppliers are the main stakeholders. Organised stakeholders for evacuation of sewage is practically non-existent. The owners of properties are responsible for cleaning up of septic tanks. Septic tank water overflows are common in the extended areas.
D. Projection of Needs
6.12 Future demand for water in the CMA has been estimated separately for the City, the Municipalities, Town Panchayats and Village Panchayats assuming different supply standards from 150-120-100 lpcd for the City, 125-100-75 lpcd for Municipalities, 100-80-60 for Town Panchayats and 80-70-60 for the Village Panchayats. The annexed table (Annexure I) shows the water demand projections for 2026 for residential, commercial and industrial uses for the three scenarios mentioned above.
6.13 The demand for various uses is summarized in the following table as high, medium and low projected needs (Scenarios 1,2 and 3 respectively).
Table No:6.5 Estimation of Water Requirements for Various Uses - CMA (in MLD)
Use
High - Scenario 1
Medium - Scenario 2
Low - Scenario - 3
Residential
1606
1296
1046
Commercial
482
324
210
Industrial
161
130
105
Total
2248
1750
1360
6.14 An assessment (September 2007) of abstractable reliable quantity of water from various sources is given in the following table:
Table No:6.6 Safe Yield from Different Sources
Sl. No.
Name of source
Safe Yield in MLD
Remarks
1.
Poondi - Sholavaram - Red Hills Lake System
227
Based on the assessment during 1997 revision of Master Plan for water supply.
2.
Groundwater aquifer from Northern Well Field
68
3.
Other sources like Southern Coastal Aquifer, Rettai Eri, Porur, etc.
5
4.
Receipt of Krishna Water from Telugu Ganga Project (when full agreed quantity of 930 MLD (12 TMC) supplied)
837
10% loss from entry point to Poondi Lake has been considered.
5.
Veeranam lake (CWSAP-I)
180
6.
Desalination Plant
200
a) 100 MLD in 2008 b) 100 MLD in 2009
7.
Local sources including Palar River in the CMA area other than City limits.
32
Based on the assessment during 1997 revision of Master Plan for water supply.
8.
Abstractable quantity of local groundwater in the city for uses other than drinking and cooking
240
9.
Waste water reuse a) Already in use b) Expected in future (SIPCOT use)
45120
From 2009
Total
1954
Source: CMWSSB
6.15 Taking into account the pressure on available sources of supply particularly from groundwater for future planning scenario – I projections may be taken as a realistic supply to be achieved. This scenario requires only 2088 MLD of potable water for residential and commercial uses which is nearly equal to the safe yield from public supply taking into account all existing sources including the sea water desalination plant for 100 mld under construction at Kattupalli. If recycling of grey water for latrine flushing purposes is taken into account it would reduce the requirement of potable water further.
6.16 The water for industrial needs are assessed between 161 to 105 mld. The present sewage treatment capacity of the Chennai system is 481 MLD and on recycling could yield at least 300-400 MLD. which can very well meet not only the 2026 industrial demand but also meet any further demand by industries as far as the quantity is concerned.
6.17 Raising water supply standards beyond scenario – III will not only increase the cost of supply and distribution but also impinge on the treatment of used water which if not undertaken would lay a heavier toll on environmental safety.