a. The Registered Technical Person (RTP) shall act as a Third-Party Agency for the purposes of coordinating joint inspections, field verifications, and other
[Figure]
technical procedures required for grant of Building Permission and Occupancy-cum-Completion Certificates under these Bye-Laws.
b. Once registered on the Designated online Building Permission Portal of H&UDD, the RTP shall be eligible to apply for and undertake building permission-related activities in any Urban Local Body (ULB), Development Authority, or agency functioning under the administrative control of the Housing & Urban Development Department, without the need for separate registration in individual jurisdictions
-
Chief Architect, Architects Organization or notified Authority by Housing and Urban Development Department ARTP prescribed.
-
Scope of Third-Party Functions:
The RTPs may be assigned any or all of the following functions—
(i) Pre-Approval Site Verification: Verification of site boundaries, existing structures, and access before plan approval.
(ii) Technical Scrutiny Support: Verification of scrutiny reports in complex or high-rise projects.
(iii) During Construction Inspection: Periodic field checks to ensure conformity of construction with sanctioned plans and building bye-laws.
(iv) Completion / Occupancy Verification: Independent inspection before grant of Completion or Occupancy Certificate.
- Integration with designated online building permission portal:
(a) The designated online building permission portal shall include a Third-Party Inspection Module for automated assignment of inspection tasks to empanelled RTPs/recognized institutes through random or rotational allocation.
(b) RTPs shall upload digitally signed, time-stamped, and geo-tagged inspection reports directly into the designated online building permission portal, linked with the unique application ID.
(c) The inspection report shall form part of the final approval record of the BPIA.
- Accountability and Independence:
a) RTPs shall have no conflict of interest in the projects they inspect.
b) Any misconduct, collusion, or negligence shall invite suspension, debarment, and other disciplinary or legal action as per Government guidelines.
-
Validity of Third-Party Certificates: Certificates or reports issued by empanelled RTPs s in the prescribed format shall be valid for the purpose of granting Building Permission, Completion or Occupancy Certificates, and may be relied upon as technical evidence in audits, appeals, or dispute resolution.
-
Government Guidelines:
BPIA may, by order, issue detailed guidelines or Standard Operating Procedures (SOPs) for:
a) Empanelment and monitoring of RTPss,
b) Standard formats of inspection reports and certificates,
c) Integration of RTPss with online system, and
d) Disciplinary mechanism for defaulting agencies.
-
Clause 2.9.3: Communication of Queries shall be deleted.
-
Clause 2.9.4 Grant or Refusal of Building Use Permit shall be deleted.
12. Clause 2.14.1 shall be replaced with the following: Responsibilities of owner and Registered Technical Person:
- Responsibility of the Owner:
a. Be responsible for ensuring that the building compliances with the Building Byelaws, master plan/zonal development plan.
b. Shall make the application for a Building Permit.
c. As prescribed appoint Registered Technical Person to undertake third-party verification of the structural design and specifications of the proposed building and, to verify and certify that the design and specifications compliance with these Building Byelaws as prescribed.
d. As prescribed, Appoint an Engineer/Architect on Record to certify that the
[Signature]
construction of the building has been undertaken as per detailed design and specifications stipulated by the R.T.P. and the Structural Engineer on Record as per clause 2.19.
e. Submit a Notice of Commencement of Construction, Plinth level inspection, Notices of Progress of Construction, and a Notice of Completion of Construction to the BPIA.
f. Inform the BPIA within 7 working days if for any reason he ceases to be the Owner of the plot for which the Building Permit has been issued or granted, regardless of whether building has commenced or not.
g. Inform the authority within 7 working days if for any reason, any of the Registered Technical Person appointed by him has been relieved of their responsibilities.
h. Ensure that no construction is undertaken during the period that the Building Permit has lapsed or has been revoked. no construction without building permission.
i. The owner or lessee of the plot shall be fully responsible for the correctness of ownership title, authenticity of documents submitted, and adherence to the sanctioned plan and provisions of these bye-laws.
j. The owner shall ensure that the construction is carried out strictly as per the approved building plan and that no unauthorized development, encroachment, or deviation is made during the course of construction.
k. The owner shall not occupy or permit occupation of the building or any part thereof without obtaining a valid Building Use / Occupancy Certificate from the Competent Authority.
- The owner shall, during construction, allow access to authorized officers of the BPIA for site inspections and shall comply with directions issued for correction of deviations or violations.
m. The owner shall remain jointly and severally responsible along with the RTP
A
for any structural failure, deviation, or violation from the sanctioned plan, as per the provisions of these bye-laws and the Jammu & Kashmir Development / Municipal Acts.
2. Responsibility of Registered Technical Person (RTP):
a. The Registered Architect / Engineer / Structural Engineer / Supervisor engaged for preparation and supervision of the building plan shall be responsible for ensuring compliance with the Master Plan / Zonal Plan, Unified Building Bye-Laws and Development Control Regulations, and all applicable building standards.