2.14 The Owner of Any Land or Groups of Owners/developers WHO Intend to Sub-divide or Layout the Land in Such Areas Into Building Plots Shall:
-
Apply along with a licensed developer to the Metropolitan-Commissioner, HMDA in prescribed format for necessary layout permission as prescribed and in accordance with these Regulations;
-
Apply with copies of necessary ownership documents, certified Revenue sketches, etc of the site;
Carry out the layout development works as per specifications and standards.
- The owner and licensed developer are required to mortgage 15% of the saleable land to HMDA as surety for carrying out the developments and complying other conditions in the given time period, in the failure of which, the HMDA shall be empowered to sell away
the mortgaged plots and utilize the amount so realized for completing the development works. In such an eventuality the developer his associates and the engineer/architect shall be black-listed and not be allowed to undertake development works in the HMDA area.
2.14.1 Minimum Area & Other Requirements for Layout Development:
-
The minimum area for layout development shall be 4 hectares. Out of the total area, 10% of the land shall be set apart for open spaces for recreation and community purposes. This will also include upto 2.5% land required to be set apart for social infrastructure.
-
From the developable area, 5% of area is to be given to Hyderabad Metropolitan Development Authority free of cost for capitalization towards provision of Master Plan facilities. This condition is applicable only to sites located outside Greater Hyderabad Municipal Corporation limits. The owner / developer has the option of paying 1.5 times the basic value of such land to Hyderabad Metropolitan Development Authority in lieu of such land to be given to Hyderabad Metropolitan Development Authority.
-
Atleast 5% of the developable land to be developed within the site for Economincally Weaker Sections of Society (EWS) housing facility with maximum plot size of 50 Sq.Mtrs and atleast 5% for Lower Income Group housing facility with maximum plot size of 100 sq. m. The developer can also opt for developing only EWS plots in lieu of LIG Housing.
-
In case it is not found feasible to provide the minimum 5% EWS and 5% LIG Plots within his site, the owner/developer is given option to develop the minimum reqired number of plots under both categories in any land within 5 Km raidus of the existing site with minimum BT road connectivity of 12 m. Alternatively, the owner/developer may handover equivalent land to Hydrabad Metropolitan Development Authority for developemt of EWS / LIG plots by Hyderabad Metropolitan Development Authority / public agency within 5 km radius of the existing site”.
-
Residential enclaves or gated community may be permitted only if a through public road of 12 mtrs width is developed at the periphery for the convenience of accessibility of other sites and lands located in the interior.
2.14.2 Other Requirements:
-
The owner shall be entitled to dispose of the non-reserved sites and non-mortgaged sites either as plots or as developed houses/buildings.
-
The Metropolitan-Commissioner, HMDA shall have the discretion of grouping the areas surrendered for EWS Housing at one place or elsewhere and disposing the area earmarked for EWS in the layout as normal building plots.
-
Residential enclaves or gated community may be permitted only if a through public road of width 12 m (40 ft.) is developed at the periphery for the convenience of accessibility of other sites and lands located in the interior as per G.O.Ms.No.168 MA dt:17.04.2012.
Hierarchy and width of roads required in Land assemblage & developments:
The width of the internal roads in a land assemblage and development for different purposes shall be regulated as follows:
| Road length (in Mt.) | Width of road for normal residential plot/use (in mt.) | Width of road for commercial, Group Housing, industrial, other non-residential plot/use or for mixed use (in mt.)- | Other requirements |
|---|---|---|---|
| Up to 300 | 9.00 | 12.00 | Utilities and services to be underground and located preferably under the footpaths and not under the main carriageway |
| Above 300 & up to500 | 12.00 | 15.00 | -Do- |
| 500 & less than 1000 | 18.00 | 18.00 | -Do- & mountable Road Divider essential |
| 1000 and above | 36.00 | 36.00 | Median and Service road development essential; Utilities and services to be underground and located preferably on service roads and under the footpaths and not under the main carriageway |
2.14.2 Splay at Road Junctions:
- Splay at road junctions shall be provided as prescribed below:
a) 3.0 mt x 3.0 mt offset/splay if the width of the road is 9.00 mt or less;
b) 4.5 mtx 4.5 mt. offset/ splay if the width of the road is above 9.00 mt but less than 18 meter.
c) 6.0 mtx 6.0 mt. offset/ splay if the width of the road is more than 18 mt in width
d) The area of such splay would be deemed to form an integral part of the road junction.
Compliance of development works:
All approved Land Pooling Schemes and Layouts would be allowed to be developed in two categories and graded accordingly, viz.,
- Grade I: Applicable for all R1 and R2 zones and in Residential Land Use in the notified Revised Master Plan for erstwhile HUDA area inside the ORR Growth Corridor viz., development works with all infrastructure facilities developed, i.e.
a) Levelling with suitable gradient and formation of all roads with proper sub-surface and camber, kerbed stones, metalling of the carriageway, side drains/gutters and central medians (for roads 18 mts and above).
b) Black topping or developing the carriageway with cement concrete ( as per BIS Code of Practice) of all roads including the main approach road up to the nearest existing public road.
c) Development of drainage and channelization of nalas for allowing storm water runoff. These may be channelized in accordance with the drainage and width requirements and in such a way as to conserve or harvest the water in nearest water body or public open space, etc.
d) Undertake street lighting and electricity facilities;
e) Provision of independent sewerage disposal system and protected water supply
system including OHT and sumps. These shall be in exclusive area over and not part of the mandatory open spaces;
f) Undertake underground ducting of all utilities and services lines either under the footpaths or central median of the roads as the case may be with proper provisions at junctions and crossings, etc.
g) Undertake greenery in the Scheme/ layout including avenue plantation, in public open spaces as per norms prescribed with a view to enhancing the environmental quality;
h) Construction of low height compound wall with iron grill to the open spaces and handing over the open spaces to Metropolitan Commissioner, HMDA along with other spaces as specified in Regulation 23, free of cost and through Registered Gift Deed.
- Grade II: Applicable for all R3 and R4 Zones and Peri-Urban Land Use in the Hyderabad metropolitan region with provisions of incremental development works in phased manner, viz.,
a) Levelling with suitable gradient and formation of all roads with sub-surface, kerb stones and footpaths, metalling of the carriageway, side drains/gutters and central median (for roads 18 mts and above). Black topping/ Cement Concreting of only the main road carriageway as well as the approach road up to the nearest existing public road shall be black topped.
2.18 Land Pooling and Area Development Schemes:
Land Pooling Schemes may be undertaken either by public authority or licensed private developers, provided the area of such a Scheme is not less than 20 Hectares. These shall apply to all new areas and greenfield sites. These shall be subject to the following:
(i) The lands covered by such land pooling scheme shall be contiguous and approachable by an existing black-topped road of 18 mts (60 feet) – where such a road does not exist the developer shall first provide for the same at his own cost; apply with copies of necessary ownership documents, Revenue sketches, etc. of the site;
(ii) A Joint Undertaking between the owners, licensed developer, qualified technical personnel for provision and compliance of the services and facilities
(iii) Apply to the Competent Authority for necessary development permission as prescribed and in accordance with these Regulations;
(iv) Carry out all the development works and facilities as per specifications and standards.
(v) The owner and licensed developer are required to mortgage 15% of the saleable land to HMDA as surety for carrying out the developments and complying other conditions in the given time period, in the failure of which, the HMDA shall be empowered to sell the mortgaged plots and utilize the amount so realized for completing the development works. In such an eventuality the developer his associates and the engineer / architect shall be black-listed the not be allowed to undertake development works in the HMDA area.
(vi) The owner shall be entitiled to dispose off the non-reserved sites and non-mortgaged plots.
(vii) Guidelines and specific conditions issued by the HMDA for undertaking the land pooling and area development schemes from time to time shall apply.
2.19 Sub-division / Amalgamation of plots permission:
Upon application to Metropolitan Commissioner, HMDA from the final plot owners or successor-in-interrest of a final approved Land Pooling Scheme; sub-divison of plots/amalgamation of plots may be permissible by Metropolitan Commissioner, HMDA. These shall be considered without again insisting on open space.However, space for public utilities may be separately insisted.