The applicant opting for Development of Green Layout and Green Development as per the norms prescribed below shall be entitled for 25% concession in the processing fee.
The various environmental planning and design measures that need to be adhered during the sustainable development of layouts are outlined as under:
a) Layout planning & design as per solar geometry – Land assemblage and developments to follow solar geometry and lay plots with longer dimension facing North and South (with a maximum deviation of 5 degree off north) and shorter dimensions facing East and West.
b) Eco-friendly transportation on-site - Adequate provision for bicycle tracks, shaded footpaths for sites equal to or more than 50 acres in size. Provide cluster layouts instead of linear layout to reduce vehicular lengths. Provisions for battery charging facilities in sites over 50 acres @ one in 50 cars parked.
c) Energy efficient street lighting – 50-100% of outdoor lighting should be met with solar photovoltaic or in combination with other renewable sources of energy, i.e., bio-mass, fuel cell, wind etc. The outdoor lighting must be provided with micro-controller based time switch.
d) Provision for minimum local amenities – Basic amenities such as grocery store, pharmacy, ATM, park should be located within 500m radius of any large residential/commercial development. If basic amenities are not available, space has to be provided to include them within the site.
e) Conserving site vegetation – Land assemblage and developments should conserve existing site vegetation and pockets of microhabitats. Existing trees should be protected where ever possible. Provisions defined to protect site vegetation retained on site during construction as described in NBC and MoEF manuals.
f) Conserving site geology – All rock formations on site need to be integrated into the layout design where ever possible taking adequate measures for stabilisation. Native flora, fauna and existing in rock clusters should not be disturbed but integrated into the layout design where ever possible.
g) Soil conservation and erosion control – Measures need to be taken before the commencement of site preparation activities in order to conserve topsoil, reduce erosion and soil pollution through site demarcation measures, spill prevention measures and temporary drainage channels with sedimentation basins.
h) Adherence to site contours – No disturbance, grading of land or stripping of vegetation shall be permitted on slopes of 25% or steeper. Any proposed disturbance for roadway crossings or utility construction shall require variance application and approval. Roads and driveways shall follow the natural topography to the greatest extent possible to minimize the cutting and grading of critical slope areas.
i) Integrated approach for Sustainable Urban Drainage System (SUDS) – Sites with areas less than 10000 sq. mtrs shall implement rain water harvesting and SUDS source control and infiltration instruments such as infiltration trenches, infiltration basins, green roofs, permeable paving, etc. Larger sites (areas greater than 10000 sq. mtrs.) shall implement other SUDS techniques integrated with the smaller techniques wherever applicable. Open sites, i.e., sites where construction development has not yet been planned shall also implement SUDS/ storm water drainage so as not to allow water logging.
j) Water conserving landscaping – Land assemblage and developments with no grey water or waste water treatment or rainwater collection, no more than 25% to be covered by lawns, exotic or ornamental plants, lawn areas should not have a slope of greater than 25%. At least 50% of the total landscaped area in the site should use water conserving vegetation such as Native species or xeriscape and at least 40% water savings should be achieved in all sites with vegetated area >50sqm by using efficient irrigation equipment.
k) Water recycling & reuse – If a site does not have access to a public sewer line and discharges waste water, an appropriate waste water treatment system should be installed and at least 75% of the total treated water should be reused on site. If a site has access to a public sewer line, grey water reuse potential of the site need to be assessed. If potential savings on potable water exceeds 20%, an appropriate grey water treatment system is recommended and at least 80% of the total treated grey water should be reused on-site.
I) Provisions for rainwater harvesting on-site – all Land assemblage and developments with a water saving potential of less than 10% of their potable water demand from rainwater collection should divert roof top and water from open areas into a percolation pit. Percolation pits should be sized appropriately and maintained regularly.
m) Zero discharge of waste water and storm water from site – All large developments (>50 acres site area) must adhere to ‘Zero Discharge’ of treated waste water and storm water outside site limits.
n) Operation & maintenance requirement for decentralized WWTS – All decentralized waste water treatment systems (WWTS) should employ qualified personnel to operate and maintain the system. The personnel involved in operation and maintenance should be a full time employee and maintenance and operation (M&O) contract should be signed with a waste water management company for its provision.
o) Provisions for safe disposal of unused treated waste water – Treated unused waste water to be disposed directly on ground for ground water recharge, used for irrigating nearby community parks, Construction activities, into a sewer line or a storm water drain or a lake, stream, pond or other surface water bodies.
p) Reducing storm water runoff and heat island effect through permeable paving – Total paved area of the site under parking, roads, paths, or any other use should not exceed 25% of the un-built site area or net imperviousness of the un-built site should not go beyond the imperviousness factor as prescribed by the NBC, whichever is more stringent.
q) Reduction of outdoor light pollution – Fixtures and fittings used for external lighting to be a minimum of 4 stars BEE rated. Provide for control devices on at least 50% of all the installed lighting fixtures. Use low albedo and rough surfaces around the luminaire to ensure that less light is reflected in the surroundings.
r) Provisions for waste management on-site – Land assemblage and developments should have a place allocated for sorting domestic waste and treating organic/biodegradable waste through composting. This space should have vehicular access and protected from wind and rain.
Commitment and responsibilities on part of Applicant: