| S.no | Particulars | Time frame | Date |
|---|---|---|---|
| 1 | 2 | 3 | 4 |
| 1 | Publication of Draft Development Plan under section 18(1) of the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973. | 10-07-2020 | |
| 3 | Hearing on objection/suggestion received after publication of the Draft Development Plan. | 90 days | 08-09-2020 to05-10-2020 |
| 4 | The recommendations of the Joint Director were sent to the Director. | 135 days | 04-01-2021 |
| 5 | Under Section 18(3) of Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973, the recommendations on Development Plan, 2031 (draft) was sent by the Director to the State Government. | 30 days | 02-02-2021 |
Number of objection/suggestion received on draft development plan - 1732
The hearing process was conducted through online mode.
The procedure (SOP) for joining online hearing of objection/ suggestion was sent to persons who had filled objections/suggestions by letter, e-mail, short messaging service (SMS), Whatsapp and voice call.