11.1 Introduction
This Chapter deals with the block cost estimates for various components of the Development Plan, the Phasing plan and also likely sources of revenue. The block estimates include the block costs of development for Social Facilities and Reservations, Transportation Infrastructure, Water supply Infrastructure, Sewerage Infrastructure, Storm
Water drains and Solid waste management.
The Draft Development Plan of SPA area indicates broad land use zoning along with the development plan roads and reservations for essential social and utility plots. The said zoning proposals will only be used as guidelines for regulating development within the framework of the development control regulations prepared for the region. The success of the plan depends on the manners in which it is to be implemented. It is found to be very difficult for any planning authority to finance and implement the Development Plan. Hence there is a need to encourage the developer to participate in the development process through various incentives at the same time share the expenditure and the monetary benefit due to the proposals of the plan. An attempt has been made in this direction to enhance the project viability.
The road widening for existing roads, proposed new road linkages and the reservations, sites earmarked for providing amenities and services etc do impose a specific responsibility over the planning authority/ special planning authority, local authority/institutes/ Trusts concerned. The land under the reservation is subject to the acquisition by the concerned bodies or the trust and institutes.
11.2 Development Plan Cost
10.2.1 Assumptions for calculation of land cost
The Annual Schedule of Rates (ASR) of lands for the year 2023-24 have been considered for arriving at the average cost of acquisition for various calculations. The Ready Reckoner rate for Karave village for the Project Area for the year 2023-24 is considered as Rs.3500 per sq.m. and accordingly the cost of acquisition for development of infrastructure comes to 4 times Rs.14,000 per sq.m (as per LARR 2013). The Cost of acquisition for 1 hectare of land is assumed as Rs.14.00 crores per hectare. Total land approx. 11 Ha. area required for infrastructure, amenities and facilities. Hence total acquisition cost of land approx. Rs. 154 Cr.

<details> <summary>seal</summary>
. 我元 </details>
10.2.2 Construction costs for buildings
The average construction cost for various buildings required to house the physical and social infrastructure are based on the ASR rates published by Departments of Registration stamps for year 2022-23 is 26,620 and for year 2023-2024 escalated by 7% year on year for current rate. The average building costs are considered as 28,483/- per sq.m. Accordingly construction cost of public utilities and amenities comes for areas of 2.4 Ha is Rs. 68.35 Cr.
10.2.3 Construction cost for infrastructure
In the Draft Development Plan of SPA, there are existing State Highway / National Highway. The proposal of widening of these roads is expected to be implemented by concerned State/Centre Govt. Authority. Also, proposed MMC corridor, Proposed Katai – Airoli Road and proposed bullet train shall be developed by concerned authorities. The rest of the DP roads proposed in the Development Plan will have to be developed by Planning Authority. The SPA area is adjacent to NMMC area and NMMC has already developed their own water supply network. Hence, water is taken from NMMC and CIDCO will developed water supply network in proposed developed area. The area under DP Road is approx. 2.0 Ha. The average construction cost for infrastructure are based on the basis of Engineering analysis is comes approx. Rs.1,56,115 per running meter including road, water supply and drainage line in proposed development area. Hence the development cost of infrastructure comes 31.22 Cr.
10.2.4 Summary of block costs
The total cost of Development comes to Rs. 253.57 crores and includes the Infrastructure Development costs for the horizon year of 2041 and reservations (Social facilities) Development costs for the horizon year 2031.
11.3 Financing the Development Plan
11.3.1 Revenue generation
Since the planning authority has decided to acquire only the land under the essential reservations and not any other land for commercial exploitation the revenue generation to meet the project cost has become difficult. It is a known fact that to implement the proposals of development plan there is always a scarcity of funds and one has to be depend upon finance from governments and financial institutes to meet the viable gap between revenue generation and the expenditure to be incurred. Efforts have been made to meet both the ends by various mean to raise the resources. Sources of revenue for SPA shall be from the following:
I. Land Linked Premium: The prevailing base FSI for SPA Area were entitled to base FS of 0.2 which could be enhanced to 0.5 on payment of premium while on the other hand
CICCO * City Institute of Development Corporation Limited Senior Planes (Development Plan) CIDCO CIDO Bépaou
other developed were having a base FSI of 1.1. In order to normalize a basic permissible FSI to 1.1 across adjacent developed area of Karave village, it is proposed to levy a land linked premium @ 5% of ASR on the entire land area while granting the development permissions. This will compensate for the sources for generating revenue for Infrastructure development. For 21.0 ha. Developed land, get a revenue around Rs. 3.67 Cr.
II. FSI Linked Premium: The DCPR proposes a basic permissible FSI with payment of Land Linked Premium as 1.1. This FSI can be enhanced to the permissible Maximum Building potential on plot as per UDCPR for 20.0 m road comes 3.0. This Maximum Building potential on the plot could be achieved with a combination of additional FSI on payment of Premium as also through TDR loading. The premium for the Residential land uses is proposed as 40 % of the ASR and for Commercial land use the same is proposed as 50% of the ASR rate. This will generate around Rs. 36.01 Cr.
III. Development charges: As per Section 124A of the MRandTP Act 1966 a Planning Authority is empowered to levy, assess and recover the Development charges that arise due to development of physical and social infrastructure. This development charge is levied on the institution of use or change of use of any land or building, or development of any land or building, for which permission is required under this Act at the rates specified. The development funds generated through the above charges shall be utilised for off-site infrastructure development. This will generate around Rs. 4.04 Cr.
IV. Disposal of Social Facility plots: Around 5% of the land coming for development is available to the Planning Authority as Social Facility plot. In order to encourage and catalyse development of social facilities and amenities, these plots shall be disposed to the concerned institution/ organization on long term lease as per the Land Disposal Policy of CIDCO and considering CIDCO's reserved price for node. This will generate around Rs. 27.04 Cr.