The key National level environmental legal requirements, which have relevance to planning and implementation, are briefly explained in this section. These are:
Environment Impact Assessment Notification 2006,
Environment Protection Act, 1986,
Forest Conservation Act, 1980,
Coastal Regulation Zone, 2011
Eco-Sensitive Zone
7.2.1 Environment Impact Assessment Notification 2006
Considering recent developments, and to ensure that the economic growth and development in our country is in conformity with regulations for environmental conservation, the Ministry of Environment & Forests has notified the Environmental Impact Assessment Notification, 2006. The environmental clearance (EC) process under implementation prior to 2006 highlighted the need to introduce specific processes /categories/ activities and also the need for new sectors such as coal washery to be brought in the ambit of the EC process due to their extent of impact on environment. The EIA Notification 2006 has notified 39 developmental sectors which require prior EC.
The MoEF has prepared EIA guidelines on each sector as identified by EIA notification 2006, which elaborates the procedure and mandatory requirements of EIA with respect to the sector. For example Manual on norms and standards for environment clearance of large construction projects has been prepared by MoEF to assist developers and project proponents’ measure and quantify environmental impacts of proposed construction, and derive mitigation options to minimise impacts.
EIA is an exercise to be carried out before any project or major activity is undertaken to ensure that it will not in any way harm the environment on a short term or long term basis. Any developmental endeavour requires not only the analysis of the need of such a project, the monetary costs and benefits involved but most important, it requires a consideration and detailed assessment of the effect of a proposed development on the environment. EIA should provide information to decision makers at early stage of the project planning cycle. It should be initiated as early as possible before the commencement of projects. If the projects secure approval, EIA should include a provision to cover the audit of the project. Following is the general list of projects that require Environmental clearance from the central government:
Nuclear Power and related projects such as heavy water plants, nuclear fuel complex, rare earths.
River Valley projects including hydel power, major irrigation & their combination including flood control.
Ports, Harbours, Airports (except minor ports and harbours).
Petroleum Refineries including crude and product pipelines.
Chemical Fertilizers.
Pesticides.
Petrochemical complexes.
Bulk drugs and pharmaceuticals.
Exploration for oil and gas and their production, transportation and storage.
Synthetic Rubber.
Asbestos and Asbestos products.
Hydrocyanic acid and its derivatives.
(a) Primary metallurgical industries, (b) Electric arc furnaces (Mini Steel Plants).
Chlor alkali industry.
Integrated paint complex including manufacture of resins and basic raw materials required in the manufacture of paints.
Viscose staple fibre and filament yarn.
Storage batteries integrated with manufacture of oxides of lead and lead antimony alloys.
All tourism projects between 200m—500 metres of High Water Line and at locations with an elevation of more than 1000 metres with investment of more than Rs.5 crores.
Thermal Power Plants.
Mining projects with leases more than 5 hectares.
Highway Projects.
Tarred Roads in the Himalayas and or Forest areas.
Distilleries.
Raw Skins and Hides.
Pulp, paper and newsprint.
Dyes.
Cement.
Foundries (individual)
Electroplating
Meta amino phenol