The availability of safe drinking water, adequate in quantity to the complete population can be rated as one of the most critical issues of BDPA. The water supply system should cover the present ‘uncovered areas’ to have 100% water supply distribution coverage, which may reduce the operation and maintenance cost. The system should provide a continuous 24 hour supply system with adequate pressure in the distribution system even at the tail ends. In BMC, raw water intake systems be designed and installed to have an enhanced water supply of 88 MGD. Suitable modifications are to be done to enhance the capacity of the intake channels so as to provide the additional supply of 25 MGD.
The drinking water demand in Khurda, Jatani, and Rural areas of BDPA in 2030 will be 200 MLD. It appears that in the absence of a centralised water supply system majority of the people are depending on ground water sources for long. But the increasing pollution of ground water sources demands that people should be provided with safe drinking
xxxvii
water, necessitating treatment of water. The future water demand of the municipalities Khurda and Jatani together with the Rural BDPA could be met by River Mahanadi, River Daya, River Kuakhai and ground water. There is an urgent need of master plan for water supply and its implementation. The tentative cost of proposed water supply system for BDPA is Rs. 1125 crores.
The level of infrastructure available for sanitation and drainage is to be drastically modified for effective management. The implementation of a proper wastewater management system is necessary to treat the huge quantities future wastewater.
Since it is necessary to provide sewage treatment facilities for 480 MLD of wastewater, a decentralised wastewater treatment system would be more appropriate. The centralised sewage treatment system appears inappropriate as it may end up with very huge sizes of sewers and various issues of conveyance in handling this huge quantity of wastewater. The possibilities of re-use of treated wastewater effluent for irrigation, gardening etc. should be looked into. The construction of treatment plants could be carried out in a phased manner on a modular/zonal basis in the planning area consistent with the future development/demand. The tentative cost of the proposed sewerage system of BDPA is around 1246 crores.
The natural drains in most of the BDPA seem to be functioning like sewers. The lack of proper sanitation and solid waste management combined with indiscriminate dumping of solid waste in the drains lead to diminish the carrying capacity of drains which cause flooding in many areas and deserve immediate attention. More emphasis is to be given in the management of drains which involves the prevention of flooding and illegal encroachments, periodic maintenance, and provisions of adequate lands for future reconstruction and augmentation activities. An organised drainage system is invariably associated with the implementation of a systematic solid waste and wastewater collection and treatment system. It is proposed that the existing drainage alignment within urban area be made permanent and also the natural drainage system be improved. Hence, the BDPA demands a full fledged drainage system.
The drainage facilities provided are very poor in Jatani, Khurda and Rural areas of BDPA. It is recommended that a drainage master plan for the entire BDPA area should be prepared. Strict implementation of the master drainage plan for these areas appears much essential. The
xxxviii
tentative cost of the proposed drainage system of BDPA is around 402 crores.
It has been felt that the solid waste management in BDPA is not in tune with the rapid development of the area. The Municipal solid waste management remains neglected. The total solid waste generation expected in BDPA would be 1500 MT/day as on 2030. It is always advisable to have decentralised compost plants for effective implementation and better efficiency and can be located as per local generation rates and availability of land. The situation demands a comprehensive and sustainable solid waste management strategy for effective implementation. The Ministry of Environment and Forests issued the Bio-medical wastes (Management and Handling) Rules, 1998 which were amended subsequently. The solid waste generation expected in BDPA is very high, providing compost treatment facilities for this huge quantum of waste, though essential, may not be practically possible in a single phase. The tentative cost for the proposed Solid Waste Management of BDPA is around 109 crores.