Sub: Modifications in the Unified Building Bye-Laws (UBBL) for Delhi 2016
S.O. 886(E).—in exercise of powers conferred by Section 57 of Delhi Development Act, 1957 (61 of 1957), the Delhi Development Authority, with the prior approval of the Central Government, hereby make the following modification in the Unified Building Bye-Laws (UBBL) for Delhi 2016.
| Sl. No. | Existing Provisions in UBBL 2016 | Proposed Amendments |
|---|---|---|
| 1 | 2.0.1Procedure | 2.0.1 Procedure (e) Building permit not required for Public Utility structures: No notice and building permit is required from the sanctioning authority for erection/ installation of Public Utility structures not exceeding 25 sqms (including its ancillary buildings purely related to any public utility) executed/promoted by Government Agencies/Organizations for enhancement of - Public Safety, Public Health and Hygiene, Environment and Climate/Pollution/ Control, Energy Conservation, Transportation, Water Supply and Sewage Disposal lines/ infrastructures, Solid Waste Management infrastructures, Electricity Supply lines, Renewable Energy or for any other such associated activities. Public Utility structures may include: 1. Public toilets/washrooms 2. Traffic and Police Control Rooms 3. Air Purification Systems, 4. Vertical gardens/green walls 5. Dhalaos (including compactor) 6. Solar panels 7. Smog towers* Note: * For Smog Towers no building permit is required from the sanctioning authority irrespective of the size of structure (including ancillary buildings). NOC from DUAC may be sought by the project proponent wherever applicable. |
| 2 | 2.5.5No further construction can be carried out without the submission/ issue of plinth level inspection report free from any deviation or deemed completion of plinth level inspection. Violation of this provision will attract penalty at same rate as that for building permit fee for sanction of building plan. | 2.5.5Part Plinth Inspection Certificate can be issued for at least one block at a time. However, no further construction can be carried out without the submission/ issue of plinth level inspection report free from any deviation or deemed completion of plinth level inspection. Violation of this provision will attract penalty at same rate as that for building permit fee for sanction of building plan. |
| 3 | 2.7.7 Procedure for inspection for OCC for moderate and high risk buildings: (a) All the external agencies shall inspect the site/ buildings and communicate to the sanctioning authority and the owner/ applicant, their NOC/refusal/objection within a period of 15 days from the date of the receipt ofthe COCCRF. | 2.7.7 Procedure for inspection for OCC for moderate and high risk buildings: (a) All the external agencies shall inspect the site/ buildings and communicate to the sanctioning authority and the owner/ applicant, their NOC/refusal/objection within a period of 15 days from the date of the receipt of the COCCRF. However, in case of warehouse/ storage buildings, the NOC/refusal/ objection is to be issued within 10 days from the date of the receipt of COCCRF. |
| 4 | 2.9.1Revocation of Building Permit The sanctioning authority shall revoke any building permit including sanction of building plan and/or OCC and take action as per law, if there has been any false statement | 2.9.1Revocation of Building Permit The sanctioning authority shall revoke any building permit including sanction of building plan and/or OCC and take action as per law, if there has been any false statement or any misrepresentation of |
| or any misrepresentation of material facts in the application on which the building permit was based. | material facts in the application on which the building permit was based. (i) The mandatory provisions of these Bye Laws like Green Buildings, Swachh Bharat toilets, child care room, disabled friendly features, Dual Piping System etc. shall be maintained and kept in proper working condition, otherwise the Occupancy-cum-Completion certificate/ Regularization certificate shall be revoked by the sanctioning authority. (ii) The provisions for parking in all type of occupancies shall be ensured otherwise the Occupancy-cum-Completion certificate may be revoked by the sanctioning authority. | |
| 5 | 7.11 Staircase Details v. Spiral Stairs (fire escape) - i. The use of spiral staircase shall be limited to low occupant load and to a building of height 9 m. ii. A spiral fire escape shall be not less than 1.5 m in diameter and shall be designed to give adequate head room. | 7.11 Staircase Details v. Spiral Stairs (fire escape) - i. The use of spiral staircase shall be limited to low occupant load and to a building of height 15 m. ii. A spiral fire escape shall be not less than 2 m in diameter and shall be designed to give adequate head room. |
| 6 | 7.11 Staircase Details g. The maximum height of riser shall be 150mm in the case of low rise residential buildings, other buildings including high rise residential building and maximum number of risers per flight shall be limited to 12 per flight. | 7.11 Staircase Details g. The maximum height of riser shall be 190mm in the case of low rise residential buildings and 150mm for other buildings including high rise residential building and maximum number of risers per flight shall be limited to 12 per flight. ( ±5 mm deviation is allowed at the time of completion as per Annexure IV, (B) ii) |
| 7 | 7.17.2 The following shall not be included in covered area for FAR and Ground Coverage calculations, subject to Fire Safety Clearances and other mandatory clearances: g. All pergolas at any floor level not exceeding 20% of Ground Coverage. n. Area of all staircase/s, Fire Tower/s in high rise/low rise buildings, excluding residential plotted development, shall not be counted in FAR and Ground coverage. p. Solar Panels at any height or level | 7.17.2 The following shall not be included in covered area for FAR and Ground Coverage calculations, subject to Fire Safety Clearances and other mandatory clearances: g. All pergolas at any floor level not exceeding 30% of Ground Coverage. n. Area of all staircase/s, Fire Tower/s shall not be counted in FAR and Ground coverage. p. Solar Panels at any height or level (including |
| (including ground level)/ terrace/ roof top subject to the max. height permitted by AAI/clearance from DFS. | ground level)/terrace/roof top subject to the max. height permitted by AAI. The space underneath shall be free from all types of storage, occupancy, use/activity, electrical installations etc. to prevent fire hazard. | |||
| 8 | 7.28 Lifts and Escalators(b) All the floors including basement and roof top/terrace shall be accessible by the lifts. The lifts provided in the buildings shall not be considered as a means of escape in case of emergency. | 7.28 Lifts and Escalators(b) All the floors including basement shall be made accessible by the lifts. The lifts provided in the buildings shall not be considered as a means of escape in case of emergency.(c) Lifts/Car lifts upto terrace/roof top be provided where the area is used for public activities. (See 7.19 vii) | ||
| 9 | 7.31Enhancing Green-Blue InfrastructureGreen and Blue features shall be developed within all sites/buildings/developments including areas under environmental protection, subject to guidelines as may be formulated from time to time for enhancing Green-Blue infrastructure in the city.The objective is to protect the existing natural assets, enhance the quantum and quality of green and blue assets, and connecting the various natural and man-made assets/elements to improve the green-blue continuum. | |||
| 10 | Table 8.1 Minimum width of staircase for different types of buildings | Table 8.1 Minimum width of staircase for different types of buildings | ||
| Assembly buildings like auditorium, theatres, cinemas etc. | 2.0m | Assembly buildings like auditorium, theatres, cinemas etc.(Addition)NOTE: The width of stairs may be accepted to be 1.50 m in case of assembly occupancy having less than 150 persons(Refer NBC PART 3 Development Control Rules And General Building | 2.0m | |
[PART IISEC. 3(ii)]
| Requirements) | |||
| 11 | 8.5.2 Electrical Services(d) All types of electrical installations such as Meter Box, Circuit breaker, Main Switch, Switchgear, Electric Vehicle Charging Port, associated equipments, which acts as energy supply points and can trigger fire hazard are not allowed under or near the staircase. If installed in Stilt area, these should be encased with fire retardant material. | ||
| 12 | 9.3.1 k. Spiral stairs can be used subject to, the use of spiral staircase shall be limited to low occupant load and to a building of height 9.0 m. further a spiral fire escape shall not be less than 1.5 m in diameter and shall be designed to adequate head room. | 9.3.1 k. Spiral stairs can be used subject to, the use of spiral staircase shall be limited to low occupant load and to a building of height less than 15 m. Further a spiral fire escape shall not be less than 2 m in diameter and shall be designed to give adequate head room. (See 7.11 v) | |
| 13 | Chapter 10 Provisions for Green Buildings 10.2 Provisions for Sanction: 1. c. Waste Water Recycle and Reuse | Chapter 10 Provisions for Green Buildings 10.2 Provisions for Sanction: 1. c. Waste Water Recycle and Reuse and Dual Piping System | |
| 14 | Annexure X Provisions for Green Buildings 1. c. Waste Water Recycle and Reuse i. Waste Water Treatment: Design an on-site treatment system to handle 100% of waste water generated in the building, to the quality standards suitable for reuse, as prescribed by Central (or) State Pollution Control Board, as applicable. | Annexure X Provisions for Green Buildings 1. c. Waste Water Recycle and Reuse i. Waste Water Treatment: Design an on-site treatment system along with Dual Piping System to handle 100% of waste water generated in the building, to the quality standards suitable for reuse, as prescribed by Central (or) State Pollution Control Board, as applicable. | |
[No. F.15(06)2016/MP/Pt.]
RAJIV GANDHI, Commissioner-cum-Secy.