These Bye-Laws may be called the Imphal Municipal Corporation Building Bye-Laws (2nd Amendment), 2022.
-
It extends to the whole of Imphal Municipal Corporation Area.
-
It shall come into force on such date as the State Government may, by notification in the Official Gazette, appoint.
2 Amendment of Section 2:
(1) Section 2(7) of the Imphal Municipal Corporation Building Bye-Laws, 2013 (herein after referred to as Principal Law) may be substituted by the following, namely:
“Bazar” means a “market” which is defined under Section 2(32) of the Manipur Municipalities Act, 1994.
(2) After Sub-section (7) of Section 2 of the Principal Law, the following subsection 7(a) shall be inserted, namely:
“Bazar Area” means the area bounded on the:
North: By Khuyathong Bazar and LIC Crossing
South: By the road from Nityaipat Chuthek to Keishampat Bridge
East: Imphal - Dimapur Road along Kangla Park
West: By Naga Nallah and Nambul River.
(3) After Sub-section (20) of Section 2 of the Principal Law, the following Subsection (20aa) shall be inserted, namely:
“EVCI” means Electric Vehicle Charging Infrastructure.
(4) After Sub-section (22) of Section 2 of the Principal Law, the following subsection (22a) shall be inserted, namely:
“LTP” means Licensed Technical Persons as per Section 2(22) of the Principal Law.
(5) After Sub-section (24c) of Section 2 of the Principal Law, the following subsection (24cc) shall be inserted, namely:
“OBPS” means Online Building Permission System.
(6) sub-section (35) of section 2 of the Principal Law shall be deleted.
3 Substitution of section 3:
Section 3 of the principal law to be substituted by the following, namely:
3 “OBPS” Online Building Permission System:
-
All the applications for buildings located within Imphal Municipal Corporation Area shall be submitted through Licence Architects or Firms registered in the name of a Licence Architect who are registered with Imphal Municipal Corporation.
-
The LTP shall make necessary site verification, examine the documents and submit the Application online to IMC along with the Building Plans in AutoCAD format and documents required as per the Building Bye-law at Chapter II of the Principal Law. The Online Building Permission System (OBPS) shall auto scrutinize the proposals. On finding the proposal as per the provisions of the Building Bye-laws and the Master Plan for Greater Imphal, the system shall generate challan for requisite fees and penalty wherever applicable.
-
On payment of requisite fees etc. the system shall auto generate instant Planning Permit and Building Permit along with approved drawing and forward the same to empaneled LTP and the Applicant with SMS and email alert. The approved drawings, the Planning Permit and Building Permit shall be in a downloadable format by the empaneled LTP and Applicant.
-
In case the proposal is not as per the provisions of the Building Byelaws and the Master Plan for Greater Imphal, the system shall return the same to empaneled LTP with email and SMS alert to the applicant with detail.
-
Authorities shall carry out post approval inspection of the proposals as and when required to ensure the adherence of the Building Byelaws and Master Plan. Any discrepancies found during the inspection, shall be treated as unauthorized as per the provisions of this Bye-law, and the Planning Permit/ Building Permit issued shall be withdrawn.
-
The buildings constructed under these clauses shall also obtain instant Occupancy Certificate on submission of all the documents as per provisions given in these bye-laws duly certified by the empaneled LTPs.
4 Amendment of section 52:
(1) sub-section (i) of section 52 shall be substituted by the following, namely:
(i) No person shall erect a building intended to be use as cinema, theater or public assembly hall or convert the use of any existing building to any such purpose, unless such building is set back at least 9M from the regular line of the public road and 4.5M on rear end side.
After sub-section (ii) of section 52, the following sub-section shall will be inserted namely:
(iii) The Ground Coverage and FAR of such buildings shall be 40 and 125 respectively.
5 Insertion of sections 54H, 54I and 54J:
After section 54G, the following sub-sections 54H, 54I and 54J shall be inserted, namely:
54H: FAR, Setbacks, Ground Coverage and Heights of Commercial/ Mixed Use Buildings
| Proposed Setbacks and Heights of Commercial/Mixed Use Buildings other than Bazar Area | |||||||||
| No. | Plot Area (sq.mt) | Maximum Ground Coverage | FAR | Maximum Height Permissible (in meters) | Minimum Setbacks proposed (in meters) | ||||
| Front | Rear | Side 1 | Side 2 | ||||||
| 1 | 90-150 | NIL | 150 | 11 | G+2 | 1.50 | 0.90 | 0.90 | 0.90 |
| 2 | 150-300 | NIL | 150 | 11 | G+2 | 2.00 | 1.20 | 1.20 | 1.20 |
| 3 | 300-500 | NIL | 150 | 13 | G+3 | 3.00 | 2.00 | 1.80 | 1.20 |
| 4 | 500-750 | NIL | 180 | 13 | G+3 | 4.00 | 3.00 | 2.40 | 1.20 |
| 5 | 750-1000 | NIL | 180 | 16 | G+4 | 5.00 | 4.50 | 4.20 | 2.50 |
| Above 16 MTS | |||||||||
| 6 | 1000-1500 | NIL | 200 | 19 | G+5 | 6.00 | 4.50 | 4.50 | 3.00 |
| 7 | Above1500 | 45 % | 200 | 22 | G+6 | 7.00 | 4.50 | 4.50 | 3.50 |
Note:
-
Requirement for parking shall be governed by Chapter X of the Principal Law.
-
For Bazar Area, the existing Setbacks, 6 feet arcade at front, 2 feet 6 inches side setbacks and 5 feet rear setbacks shall continue. Maximum Ground Coverage permissible is 80%. FAR permissible is 300.
54I: FAR, Setbacks, Ground Coverage and Heights of Institutional/ Educational Buildings
| Proposed Setbacks and Heights of Institutional/Educational Buildings |
7 After Section 71 of the Principal Law, the following Section 71A shall be inserted, namely:
71A: In-Building Solutions for Common Telecommunication Infrastructure: For installation of In-Building Solution (IBS) / Smart Connectivity infrastructure, the procedure laid down in Annexure-C shall be followed.
8 Insertion of a new Chapter XV:
After Chapter XIV of the Principal Law, the following new chapter XV shall be inserted, namely: