As per recommendations of the BIS, any land area above 600 m in height from the mean sea level or any land area with an average slope of 30 degrees considering the sensitive and fragile ecosystem shall be considered a hilly area. The entire Greater Imphal Area is located 600m above mean sea level. The Risk-Informed GIS-Based Master Plan identifies the areas under the following categories of slopes in degrees.
| (a) | 0 | - | 20 |
|---|---|---|---|
| (b) | 21 | - | 30 |
| (c) | 30 | - | above |
92.1 Permission of construction on slopes/gradients
Considering the sensitive and fragile ecosystem, no construction will be permitted in the areas which have a slope of more than 30 degrees. Permission of development only upto two floors or 7m height in areas which have a slope of 21-30 degrees.
92.2 Restricting cutting of steep slopes
Considering the sensitive and fragile ecosystem, no cutting of slopes will be permitted in the areas which have a slope of more than 30 degrees.
93
Flood Risk Prone Areas
93.1 Buffer Zone for Rivers
Prohibit any new construction within the designated buffer zones to minimize human exposure to flood risk and preserve the natural integrity of natural eco-systems, the following table indicates the buffer that is no new construction zone:
| Reach | Left Bank Boundary | Right Bank Boundary |
| Imphal River | ||
| Koirengei to Lilong | 55m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream | 55m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream |
| Nambul River | ||
| Within Greater Imphal Area | 30m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream | 30m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream |
| Merakhong River | ||
| Yurembam to Tiddim Road crossing | 22.5m from the mid stream | 22.5m from the mid stream |
| Tiddim Road crossing to Langpok | 24.20m from the mid stream | 24.20m from the mid stream |
| Iril River | ||
| Sawombung to Lilong | 50m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream | 50m from the mid stream or 6m from the outer toe of the bund whichever is farther from the mid stream |
| Kongba River | ||
| Chairenthong to Kyamgei | 35m from the mid stream | 35m from the mid stream |
No person shall undertake any activity within the prohibited area or restricted area except with the previous permission of the Flood Zoning Authority constituted under the Manipur Flood Plain Zoning Act, 1978.
93.2 Construction in High Flood Risk Area
In High Flood Risk Areas identified in the Risk-Informed GIS-Based Master Plan for Greater Imphal, the plinth level should be 1m above the highest flood level of the surrounding areas.
3. Insertion of Chapter XVII
After Chapter XVI of the Principal Law, the following new Chapter XVII shall be inserted namely: