The 15 November, 2012
No. CCP(NCR)/FDP-2031/GGN/2012/3541 .- Whereas, the Final Development Plan – 2021 A.D. of Gurgaon Manesar Urban Complex was published in the Official Gazette vide notification no. CCP (NCR)/ FDP (G) / 2007/359, dated 5th February, 2007 for a projected population of 37 lacs.
And whereas, in a meeting held under the Chairmanship of Hon‟ble Chief Minister, Haryana on 14.07.2009, it was decided to increase the sector density from 80 PPA to 100 PPA and from 100 PPA to 120 PPA in all the Development Plans of the towns/ cities in the State. While preparing the proposal, it was observed that the sector roads leading from sectors-58/61, 59/60, 61/62, 60/63, 62/65, 63/64, 65/66 and sectors 64/67 were ending abruptly. Accordingly, it was proposed to improve the road network of these sectors. Besides, it was observed that a Nallah (Kost) passed through sector-58 to 66 in a haphazard manner. A technical Committee conducted a study and suggested for realigning the nallah along Southern Peripheral Road. The Development Plan was revised for the perspective year of 2025 AD after following prescribed procedure i.e. consideration by District Level Committee, District Planning Committee, State Level Committee, inviting objections from public by publication of Draft Plan in the Official Gazette vide notification no. CCP(NCR)/DDP(G)/2010/3785 dated 04.10.2010 and consideration of all objections/suggestions by the Government. The Final Development Plan 2025 AD was published in the Official Gazette vide notification No. CCP(NCR)/ FDP (G)/2011/1386, dated 24th May, 2011. Resultantly, there was no substantive change in the urbanizable area or land use plan except marginal increase in the urbanizable area of the Development Plan to the extent of only 1.18% (approx.).
And whereas in the Development Plan of 2021 AD as well as 2025 AD, a large area measuring 4570 hectares was earmarked for setting up of SEZs. The scenario regarding setting up of SEZs has undergone sea change since notification of these Plans and virtually there are no more takers for SEZs now. Even the already notified SEZs are not being implemented and resultantly, the landowners of such land were demanding replanning of their land so that they were able to utilize the same for some other purpose. Therefore, on a reference received from the Industries Department, the exercise to replan this area was initiated. This was the primary reason for initiating revision of the Final Development Plan of 2025 AD. However, while undertaking the revision, following parameters were also taken into account:-
i. All the Development Plans of major towns / cities in the State are being prepared for a perspective period of 2031 AD.
ii. In the 2nd meeting of the “Cabinet Sub Committee on Infrastructure” held on 15.02.2011, it was decided that the use of land, which was under acquisition by the Industries Department along KMP Expressway be converted to Agriculture Zone after release with a condition that no CLU or licence would be granted in this area, so that same is used only for agricultural purposes.
The Plan was placed before the District Planning Committee (constituted under sub-section (1) of section 203 B of Haryana Municipal Act, 1973 (Act 24 of 1973), read with rule 3 of the Haryana Constitution of District Planning Committee Rules, 1997 as mandated under article 243 ZD of the constitution) / District Level Committee in the meeting held on 09.08.2012 and it was approved with the following observations / suggestions:-
The city has been planned for a projected population of 41.65 lacs but no provision had been made for a University. Hence, provision of land for University over an area of approximately 200 hectares may be made in the plan along the newly proposed bye-pass above sector 68. Keeping in view this additional allocation of land, the small pockets / strips of public and semi public uses proposed along the sector dividing roads in sector 71 & 89A may be eliminated and the site of town park proposed in sector 89A may be proposed along sector dividing road of sector 89A-95A. A part of the eliminated strip of public and semi public use in sector-71 in continuation of commercial belt along SPR may be converted into commercial and rest of its part may be proposed for residential use. Similarly, the proposed eliminated strip of land for public and semi public uses in 89A between residential zone and town park (after interchange in their location) may be converted into residential zone. This will improve upon the environment of the surroundings in residential sectors. Besides, approximately 50 hectares of land may also be reserved for affordable housing in sector 68 adjoining newly proposed university site, as has been done in case of Sohna and Farukhnagar Development Plan to provide housing to low and medium income group.
Apart from above, the Committee also suggested to extend the sector dividing road of sector-69/70 (V2 type) upto the proposed bye-pass to complete the circulation system of sector roads of expanded sector-68. In order to improve the road network of sector-70A, the Committee proposed to eliminate the eastern outer road of sector - 70A, as the same is no more required after proposed extension of sector dividing road of sector-69 & 70 and
also to extend the western outer road of sector-70A upto the proposed extended road of sector-69-70. The land use of triangular space generated due to this amendment is proposed as town park.
ii. As large chunk of additional land has been proposed for public and semi public use (university) in sector 68. Hence, land use of half of the public and semi public zone proposed in sector 115 may be converted into commercial as it will fetch revenue to Government exchequer being its proximity to Delhi. It is also suggested that rest of public and semi public zone in this sector should be exclusively developed by Government. It will improve the aesthetics of the entry point of Gurgaon from Delhi side.
iii. The right of way of the newly proposed bye-pass starting from Sohna Road to NH-8 may be increased from 75 m to 90 m with 30 m green belt on either sides and width of additional link road for Sohna starting from sector dividing road of sector 63 & 64 of GMUC may be increased from the 60 m to 90 m with 30 m green belt on either sides.
iv. As requested by Chief Administrator, HUDA, a 60 m wide new road in sector-54 may be proposed to provide connectivity to HUDA acquired land with Golf Course Road (V2 type). This road may further be extended upto Gurgaon-Faridabad road.
v. The land use of already acquired HSIIDC land on southern side of N.H.-8 along KMP may be changed to industrial use as requested by STP, HSIIDC.
vi. The sector dividing road of sector-101 & 104 may be slightly amended to align it with sector dividing of sector 9A & 9B and a flyover may also be proposed on the junction of these sector roads with existing railway line. The land use of triangular space generated due to minor change in the alignment of sector road, which part of sector 101 (public utility zone) will remain unchanged. This amendment and flyover will provide a great loop to connect northern and southern side of Gurgaon.
vii. The Municipal Corporation, Gurgaon boundary beyond sector 67A may be amended as per actual.
viii. The existing Gurgaon- Sohna road, beyond urbanization, may be widened to 60m with 50m green belt on either sides to bring it at par with the Draft Development Plan of Sohna-2031AD.
ix. The existing Naurangpur road, above sector 79 up to proposed bye-pass may be widened to 60 m.
x. The fashion hub, world trade hub and entertainment hub proposed along KMP Expressway may also be depicted in the draft plan.
And whereas all the suggestions of the DPC / DLC were incorporated in the Plan and it was placed before the State Level Committee in the meeting held on 29.08.2012. The Committee accepted all the suggestions made by DPC/DLC and approved the following:-
i. The outer V-2 road of Sector 79 is taking a sharp turn, which needs to be smoothened. Hence, the sector dividing road of Sector-79 & 79A be straightened and it be extended up to proposed Greater Southern Peripheral V 2(e) Road along the flowing green. Similarly, the proposed extension of South-Western sector V2 road of Sector 79 may also be straightened and the outer loop of Sector 79 be eliminated.
ii. The Committee noted that there are two sharp curves in continuum in the proposed Greater Outer Southern Peripheral V2(e) road when it passes by Sector 79, hence, the curvature at this stretch of the road needs to be straightened for smooth flow of traffic.
iii. In sector 79, the green belt along proposed Greater Southern Peripheral V 2(e) Road be increased from 30 metres to 50 metres towards sector side upto flowing green.
iv. The land use of space generated between V 2 roads & V 2(e) road and residential zone of Sector 79 after elimination of outer road of sector 79 be changed from agriculture zone to residential zone. Accordingly, the area statement and projected population be updated.
v. The sector dividing V 2 road of sectors M8-M11 (V2 Type) be extended up NH-8 along Orbital Rail Corridor.
vi. The non-feasible portions of north-eastern side V 2(d) road of Sector M 13 adjoining village Bhangrola & Sector M 15 adjoining village Kakrola due to spill-over of village abadies falling in its alignment, be realigned as per site conditions.
vii. The sector dividing V 2 road of sectors 81-86 that terminates at north-eastern side V 2(d) road of sector M15 be extended upto the junction of sector dividing V 2 road of sector M6-M7 with the sector dividing V 2 road of sectors M6, M7-M15.
viii. After creation of new road as mentioned at para (vii) above, the road portion below this newly created road be eliminated up to Sector M6A, as most part of this road is not feasible at site due to spill over of abadi of village Naharpur Kasan falling in the alignment of the road. Further, the junction formed by the sector dividing road of Sector M6-M6A with north-eastern side of M6A be improved by giving smooth curvature.
ix. The sector dividing road of sector 35 (industrial) -74A (commercial) be eliminated as the same is not feasible on the ground and a line be drawn to segregate these sectors.
x. Regarding new V2 type road proposed in sector 54 for providing connectivity to the acquired land of HUDA on the recommendation of DPC / DLC, the Committee observed that the junctions of
existing V3 road and proposed V2 road on Gurgaon-Faridabad road (State Highway) are too close to each other, which is hazardous and would make this part of the road accidental prone. As a better and wider link has been proposed, hence, the existing V3 road will be eliminated upon the construction and operationalisation of proposed V2 type road.
xi. A 50 metres wide corridor be provided along GWS Channel through the site proposed for dairy farming/gaushala for laying services.
xii. Regarding merging of additional area in sector-37D instead of creating a new sector as 37D part, the Committee noted that the area of sector 37D was inadvertently calculated on the higher side and the Department of Town and Country Planning granted licenses for setting up group housing colonies accordingly. In view of this fact, the additional residential area carved out of the defreezed land of erstwhile SEZ, has not been given a separate number. Instead, it has correctly been merged with sector 37D.
And whereas all the above suggestions of the State Level Committee were incorporated in the Draft Development Plan-2031 AD and the Draft Plan was published in the Official Gazette vide Haryana Government, Town and Country Planning Department notification No. CCP(NCR)/DDP-2031/GGN/2012/2864 dated the 4 m September, 2012 for inviting objections / suggestions from the Public;
Now, after considering all objections/suggestions received on said Draft Plan and in exercise of the powers conferred by sub-section (7) of section 5 of the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act, 1963 (Punjab Act 41 of 1963), the Governor of Haryana, hereby publishes the Final Development Plan 2031 AD for Gurgaon-Manesar Urban Complex, along with restrictions and conditions as given in Annexures A and B proposed to be made applicable to the controlled areas specified in Annexure B.
Drawings
-
Existing Land Use Plan drawing No. DTP(G) 1936/2010, dated the 1 6 t h April, 2010 (already published in Haryana Government Gazette on 2 4 t h May, 2011 vide Haryana Government, Town & Country Planning Department notification No. CCP(NCR)/FDP(G)/2011/1386 dated the 24th May, 2011).
-
Final Development Plan-2031 AD Drawing No. DTP(G) 2104/2012, dated the 9th November, 2012.
It is clarified that in the explanatory note of the Draft Development Plan-2025 AD for the Controlled Areas of Gurgaon-Manesar Urban Complex which was notified by the Department on 04.10.2010, the definition of sector density and colony density was in terms of number of persons per hectare in sector area or colony area. This sector density was also specified as 250 PPH in the Residential use under the heading description of land uses under Annexure-A. However, the density was shown in terms of „persons per acre‟ in the enclosed drawing of the Draft Development Plan. A similar position existed while notifying the Final Development Plan of Gurgaon-Manesar Urban Complex on 24.05.2011. However, the sector density in the definition as well as the plan were correctly shown in terms of „persons per hectare‟ in the Draft Development Plan of Gurgaon-Manesar Urban Complex notified on 04.09.2012, inviting objections/suggestions from the public. The Final Development Plan is being notified accordingly showing density in terms of „persons per hectare‟. In addition to above, it is also clarified that the density of part sectors 42, 43, 53 & 54 was increased from 100 PPA to 250 PPA equivalent to 625 PPH in the year 1995 while granting license for a Group Housing Colony which remains unchanged till date.